在江西水泥厂扩建工程中,我处以总承包单位承担了全部机电设备安装任务。安装工作从1984年12月大窑吊装开始,于1986年11月投料点火,一次试车成功。提前一个月实现建厂工期,安装质量达到设计要求,无重大事故,创造了设备安装的较好成绩。群策群力,加快安装进度江西水泥厂扩建的是采用电子计算机控制生产的新型干法工艺线,施工周期短,技术要求高,电子计算机是国内组装的,控制盘柜解体运输,为现场组装和调试增加了困难。公司派有经验的工程师常驻工地指导安装工作,技术人员与老工人相结合,研究图纸资料,查出
In the Jiangxi cement plant expansion project, I assumed the general contractor to undertake the installation of all mechanical and electrical equipment. The installation work began in December 1984 when the kiln was hoisted. In November 1986, the material was ignited and the test was successful. One month in advance to achieve the construction period, the installation quality meets the design requirements, no major accidents, and create a better performance of equipment installation. Working together to speed up the installation progress Jiangxi Cement Factory expanded its new dry process line using computer controlled production. The construction period is short and the technical requirements are high. The electronic computer is assembled in China and the control cabinet is disassembled and transported, increasing the number of on-site assembly and commissioning. Difficulties. The company dispatches experienced engineers to work at the site to guide the installation work. The technicians combine with the old workers to study the drawings and documents.