本文叙述了防渗墙方法在受潮汐活动影响的堆土场标高以下矿石回采中的应用。这个厚32英寸(1英寸=2.54cm)、面积30万英尺~2(1英尺~2=0.09289m~2)的防渗墙用约200磅/英寸~2(1磅/英寸~2=6.8948MPa)的低强度塑性混凝土构成,可承受约100英尺(1英尺=0.3048m)的水头。在高度渗水的海边排土场中构筑的这道防渗墙将使该露天坑边坡扩帮300英尺,因此可以获得开采4年的附加矿石储量。本文对这项工程从其开始到采矿,包括现场调查研究、工程设计的忧虑和复杂问题、施工障碍及其克服办法都进行了评论。文章结尾部分说明了所用的监测系统和迄今这道防渗墙的性能。
This paper describes the application of cutoff wall method in the recovery of ore below the elevation of the dump site affected by tidal activity. The cut-off wall, 32 inches thick (1 inch = 2.54 cm) and 300,000 feet 2 (1 ft 2 = 0.09289 m 2) thick, is about 200 pounds per square inch (2 pounds per square inch to about 6.8948 inches) MPa) low-strength plastic concrete that can withstand about 100 feet (1 foot = 0.3048m) head. The cut-off wall constructed in a highly seepage-prone beach dump will allow the open pit slope to expand 300 feet, thus providing additional ore reserves for four years of mining. This article reviews the project from its inception to its mining, including on-site investigations and studies, engineering design concerns and complex issues, construction obstacles and how to overcome them. The end of the article describes the monitoring system used and the performance of this cutoff wall so far.