南京钢铁厂大烧渣氯化球团基础工程,需要大量20~30米的长桩,加固在长江江岸边的软弱地基中,以满足日本设计的荷重的要求。而江苏地区高的桩架机械设备有限。我公司技术人员经过努力认真试验,大胆革新,在省机械化公司的大力协作下,在学习上海静力压桩的基础上,采用硫磺胶泥接桩,在动荷重作用下打桩,应用到引进项目的桩基工程中,这就进一步发展了这一新工艺、新技术。由于它在江苏和南京地区第一
The large-scale slag chlorination pellet foundation project of the Nanjing Iron and Steel Plant requires a large number of long piles of 20 to 30 meters to be reinforced in the soft foundation on the bank of the Yangtze River to meet the requirements of the Japanese design load. In Jiangsu, the high pile machinery equipment is limited. Our company’s technicians have tried hard and boldly reformed. Under the strong cooperation of the provincial mechanization company, on the basis of learning the static pile in Shanghai, the piles were piled with sulfur cement and piled under the action of dynamic load to apply to the project. In pile foundation engineering, this further developed this new process and new technology. Because it is the first in Jiangsu and Nanjing