工业厂房挂脚手架是在毛主席无产阶级革命路线指引下,在批林整风运动的推动下试验成功的。去年初,上级党委交给我公司三厂会战的艰巨任务,我工区直接担负着其中二个厂的重点项目,建筑面积近十万平方米,任务大,工期紧。要按期完成上级领导交给的任务,主要困难是架子工少,杉槁不足,初步计算要完成这二个厂的任务,至少需要20000
The scaffolding of industrial plants was successfully tested under the guidance of Chairman Mao’s proletarian revolutionary line and promoted by the forestry rectification movement. At the beginning of last year, higher-level party committees handed over to the arduous task of the company’s three factory battles. Our work area was directly responsible for the key projects of two of them, with a construction area of nearly 100,000 square meters, a large task, and a tight schedule. To complete the tasks entrusted by the superiors on schedule, the main difficulty is the shortage of laborers and the lack of cedars. The preliminary calculations require the completion of the tasks of these two plants, which require at least 20,000 yuan.