1前言电站锅炉安装过程中焊接是工作量大且又重要的施工工序。焊缝质量检验是保证焊接质量的重要环节,无损检测又是焊缝质量检验的主要手段,其中大量的对接接头要进行射线探伤。在《蒸汽锅炉安全技术监察规程》(1996)规定了对接接头的射线探伤应按GB 3323—87《钢熔化焊对接接头射线照相和质量分级》的规定执行。射线照相的质量要求不应低于AB级。额定蒸汽压力大于0.1MPa的锅炉,对接接头的质量不低于Ⅱ级为合格。而电力系统也有其行业射线探伤标准,其最新版本为DL/T
1 Introduction Power station boiler installation process is a heavy workload and important construction process. Weld quality inspection is to ensure the quality of an important part of welding, non-destructive testing is the main means of weld quality inspection, of which a large number of butt joints for radiographic testing. In the “steam boiler safety technology supervision regulations” (1996) provides that the butt joint radiographic testing should GB 3323-87 “steel fusion welding butt joint radiography and quality grading” requirement. Radiographic quality requirements should not be less than AB level. Rated steam pressure greater than 0.1MPa boiler, the quality of butt joint is not less than Ⅱ grade qualified. The power system also has its industry standard for ray tracing, the latest version of which is DL / T