论文部分内容阅读
一、设置要求JGJ 59—2011《建筑施工安全检查标准》第3.3.4条:层间防护(1)作业层脚手板下应采用安全平网兜底,以下每隔10m应采用安全平网封闭。JGJ 130—2011《建筑施工扣件式钢管脚手架安全技术规范》第9.0.11条:脚手板应铺设牢靠、严实,并应用安全网双层兜底,施工层以下每隔10m应用安全网封闭。二、相同与矛盾之处相同之处:两个规范都要求在脚手板下应采用安全网兜底,以下每隔10m应用
First, the set requirements JGJ 59-2011 “Construction Safety Inspection Standards” Article 3.3.4: Interlayer protection (1) Operating under the scaffolding should be used safety flat bottom, the following every 10m should be closed with a safety net. JGJ 130-2011 “Construction Fastener Steel Scaffolding Safety Specifications” Article 9.0.11: Scaffolding should be laid solid, firm, and the application of safety net double bottom, every 10m below the construction layer safety net closed. Second, the same and contradictory place of the same place: Both regulations require that the scaffolding plate should be used under the safety net, the following application every 10m