摘要 在高压线下施工作业存在较大的安全风险,本文以广州市某工地在高压线塔限高条件下进行地下连续墙施工为例,详细介绍了在此特殊工况下为保证施工安全与质量所采取的各项措施,包括高压线高度的现场实测、大型施工设备的选择、钢筋网片对接等,具有一定的施工代表性,可供其它类似工程借鉴。
关键词 地下连续墙,高压线塔,高度测量,设备限高措施,钢筋网片对接,工程质量控制
Abstract: High pressure line in construction operation there is greater safety risk, and this paper Guangzhou a certain site is in the high tension line the height limit tower under conditions of underground continuous wall construction as an example. The paper introduces in this special condition to ensure the construction safety and quality measures taken, including the height of the high tension line and the actual, large construction equipment selection, reinforcement fabric piece docking, etc, and has a certain construction representative, available for other similar engineerings.
Key Words: underground continuous wall, high tension line tower, height measurement, and equipment, high limit measures, reinforcement fabric piece docking, engineering quality control
中图分类号: TM726.1文献标识码:A 文章编号:
1工程概况
本工程基坑长28.1m,宽10m,深13.5m,采用地下连续墙+混凝土内支撑体系。地下连续墙既是土方开挖、地下结构施工时的挡土截水支护结构,又是作为工程永久结构的一部分,厚度为0.8m,深18.75m,钢筋网片长18.25m。基坑上方有110kv高压电缆跨过,现场进行连续墙钢筋网片吊装时,吊装高度有与高压架空线冲突的危险,需要采取特别的施工措施。
2限高条件下连续墙施工应对措施
2.1实地测量
由于高压线处于始发井基坑上空,施工前需先对高压电缆的具体三维坐标进行测量核准,标记出高压电缆与基坑的平面投影与竖向高程的相对位置,以此作为下步具体施工安全措施的制定依据。见图1
图1 高压电缆与竖井平面关系及警戒线设置图
经过对现场高压电缆多次测量,高压电缆与地面高差为26.3m(北)、25.25m(南),成槽机最大垂直高度为17.4m,履带式起重机最大高度为17.98m,(全站仪测量高程,误差为±10mm)。
2.2设定安全警戒范围
依据《施工现场临时用电安全技术规范》(JGJ46-2005)中4.1.4 条:起重机严禁越过无防护设施的外电架空线路作业。在外电架空线路附近吊装时,起重机的任何部位或被吊物边缘在最大偏斜时与架空线路边线的最小安全距离应符合表1规定
表1 起重机与架空线路边线的最小安全距离
电压(KV)安全距离(m) <1 10 35 110 220 330 500
沿垂直方向 1.5 3.0 4.0 5.0 6.0 7.0 8.5
沿水平方向 1.5 2.0 3.5 4.0 6.0 7.0 8.5
本工程上方最近点高压电缆为110千伏电缆,其垂直方向安全净距要求为5m,上部220千伏电缆垂直方向安全净距要求为6 m。实际施工控制中以水平安全间距不小于6.0m,垂直安全间距不小于6.5m,即控制设备运行高度不大于25.1-0.6-6.5=18 m,控制设备距离高压线水平距离为6 m,则施工时在地面设置警戒标志(线)。见图2
图2 高压线下起重吊装示意图
2.3机械选择
经现场反复测量,始发井使用的机械设备中,履带吊机的高度最高。因此,在履带式起重机进场组装时,起重机配置高度为:机体高度(1.8 m)+标准节(6 m +6 m +3 m)+吊钩顶部凸出部分(1.18 m)=17.98 m,控制其最大吊装高度不超过18 m。另外吊装时在吊臂顶点悬挂18m长的线锥作为安全高度控制标志,确保钢筋网片吊装时与高压线保持安全距离。
2.4钢筋网片制作与安放
由于钢筋网片长度为18.2米,无法直接用改装后的履带吊进行整体吊装,须进行分节制作,再进行对接。
2.4.1钢筋网片的制作安装
钢筋网片在槽段成槽之前现场分节制作完成,围护桩钢筋网片施工时按照设计长度分节制作,将钢筋网片制成标准段和调整段。钢筋网片的加工根据设计施工图、施工工艺和规范要求进行。
设计要求钢筋网片水平分幅接头位置需布置在第二道支撑以下1.7~1.8m范围内,第二道支撑底部相对标高为6.25m,即分节部位设定在钢筋网片7.95~8.05m的范围内,现场钢筋网片分节尺寸示意图如图5所示:
现场钢筋网片制作需提前预留钢筋搭接焊长度,保证钢筋网片对接焊接长度与质量。
2.4.2钢筋连接及安放
第一步将钢筋网片下半部分先吊进槽内,用横担将钢筋网片固定在导墙上。
第二步将钢筋网片的上半部分吊起,与槽内的钢筋网片焊接成整体。
第三步钢筋网片焊接完成后,形成一幅整体的钢筋网片,然后慢慢吊起,抽去横担,将整幅钢筋网片放进槽内,完成吊装。
3施工质量保证措施
3.1钢筋网片对接保证措施
钢筋网片加工时,将两段钢筋网片同时摆放在加工平台上,一同制作,纵筋一一对应,预留好搭接焊长度,形成一幅整体笼,在吊装焊接时便于操作,防止因加工钢筋网片尺寸不一,造成相互对接不上的情況发生。钢筋网片焊接时,每面两人先将四角钢筋绑扎焊接好,再焊接中间纵筋。钢筋工辅助将其它接头绑扎调整好,便于焊工操作,加快焊接进程。6米的钢筋网片,接头共有82个,按每人每小时7个接头,大概3~4个小时完成,可以满足施工要求。
钢筋网片纵向主筋焊接完成后,须补齐横向分布筋,并将焊渣一一敲除,质检、监理工程师对焊接接头的焊缝长度、质量检查合格后方能进行钢筋网片的吊装。
3.2防止槽壁坍塌措施
由于部分槽段钢筋网片需要进行对接,对接作业时间长达4个小时,加上钢筋网片起吊、对位,等待混凝土到场,因此槽段在完成清孔后将等待约6个小时之久,对泥浆护壁的效果提出了很高的要求。为保证清孔后槽段的安全,工程采用以下措施:
(1)选用优质膨润土制浆,比常规泥浆提高一个档次,并将泥浆比重适当调大至1.1g/cm3,确保槽段护壁质量;
(2)选用小型泥砂分离器进行清槽(图10);
(3)在钢筋网片焊接时严禁机械、车辆通过,防止挤压造成塌槽;
(4)钢筋网片整体下放后,对槽底沉渣重新进行测量,若不满足沉渣厚度要求须进行泥浆置换循环。
4结论
高压电缆下进行连续墙钢筋网片的吊装作业存在着较大的安全风险,高强度的对接和焊接对质量和安全风险都较大。在此特殊工况下,如何保证工程安全及质量的管理经验,希望本文可以给同行们一些借鉴。
参考文献
[1] 地下铁道工程施工及验收规范. 北京:中国计划出版社,2004
[2] 叶可明. 上海建筑施工新技术[M]. 北京:中国建筑施工出版社,1999
[3] 丛蔼森. 地下连续墙的设计施工与应用[M]. 北京:中国水利水电出版社,2002.
注:文章内所有公式及图表请用PDF形式查看。
关键词 地下连续墙,高压线塔,高度测量,设备限高措施,钢筋网片对接,工程质量控制
Abstract: High pressure line in construction operation there is greater safety risk, and this paper Guangzhou a certain site is in the high tension line the height limit tower under conditions of underground continuous wall construction as an example. The paper introduces in this special condition to ensure the construction safety and quality measures taken, including the height of the high tension line and the actual, large construction equipment selection, reinforcement fabric piece docking, etc, and has a certain construction representative, available for other similar engineerings.
Key Words: underground continuous wall, high tension line tower, height measurement, and equipment, high limit measures, reinforcement fabric piece docking, engineering quality control
中图分类号: TM726.1文献标识码:A 文章编号:
1工程概况
本工程基坑长28.1m,宽10m,深13.5m,采用地下连续墙+混凝土内支撑体系。地下连续墙既是土方开挖、地下结构施工时的挡土截水支护结构,又是作为工程永久结构的一部分,厚度为0.8m,深18.75m,钢筋网片长18.25m。基坑上方有110kv高压电缆跨过,现场进行连续墙钢筋网片吊装时,吊装高度有与高压架空线冲突的危险,需要采取特别的施工措施。
2限高条件下连续墙施工应对措施
2.1实地测量
由于高压线处于始发井基坑上空,施工前需先对高压电缆的具体三维坐标进行测量核准,标记出高压电缆与基坑的平面投影与竖向高程的相对位置,以此作为下步具体施工安全措施的制定依据。见图1
图1 高压电缆与竖井平面关系及警戒线设置图
经过对现场高压电缆多次测量,高压电缆与地面高差为26.3m(北)、25.25m(南),成槽机最大垂直高度为17.4m,履带式起重机最大高度为17.98m,(全站仪测量高程,误差为±10mm)。
2.2设定安全警戒范围
依据《施工现场临时用电安全技术规范》(JGJ46-2005)中4.1.4 条:起重机严禁越过无防护设施的外电架空线路作业。在外电架空线路附近吊装时,起重机的任何部位或被吊物边缘在最大偏斜时与架空线路边线的最小安全距离应符合表1规定
表1 起重机与架空线路边线的最小安全距离
电压(KV)安全距离(m) <1 10 35 110 220 330 500
沿垂直方向 1.5 3.0 4.0 5.0 6.0 7.0 8.5
沿水平方向 1.5 2.0 3.5 4.0 6.0 7.0 8.5
本工程上方最近点高压电缆为110千伏电缆,其垂直方向安全净距要求为5m,上部220千伏电缆垂直方向安全净距要求为6 m。实际施工控制中以水平安全间距不小于6.0m,垂直安全间距不小于6.5m,即控制设备运行高度不大于25.1-0.6-6.5=18 m,控制设备距离高压线水平距离为6 m,则施工时在地面设置警戒标志(线)。见图2
图2 高压线下起重吊装示意图
2.3机械选择
经现场反复测量,始发井使用的机械设备中,履带吊机的高度最高。因此,在履带式起重机进场组装时,起重机配置高度为:机体高度(1.8 m)+标准节(6 m +6 m +3 m)+吊钩顶部凸出部分(1.18 m)=17.98 m,控制其最大吊装高度不超过18 m。另外吊装时在吊臂顶点悬挂18m长的线锥作为安全高度控制标志,确保钢筋网片吊装时与高压线保持安全距离。
2.4钢筋网片制作与安放
由于钢筋网片长度为18.2米,无法直接用改装后的履带吊进行整体吊装,须进行分节制作,再进行对接。
2.4.1钢筋网片的制作安装
钢筋网片在槽段成槽之前现场分节制作完成,围护桩钢筋网片施工时按照设计长度分节制作,将钢筋网片制成标准段和调整段。钢筋网片的加工根据设计施工图、施工工艺和规范要求进行。
设计要求钢筋网片水平分幅接头位置需布置在第二道支撑以下1.7~1.8m范围内,第二道支撑底部相对标高为6.25m,即分节部位设定在钢筋网片7.95~8.05m的范围内,现场钢筋网片分节尺寸示意图如图5所示:
现场钢筋网片制作需提前预留钢筋搭接焊长度,保证钢筋网片对接焊接长度与质量。
2.4.2钢筋连接及安放
第一步将钢筋网片下半部分先吊进槽内,用横担将钢筋网片固定在导墙上。
第二步将钢筋网片的上半部分吊起,与槽内的钢筋网片焊接成整体。
第三步钢筋网片焊接完成后,形成一幅整体的钢筋网片,然后慢慢吊起,抽去横担,将整幅钢筋网片放进槽内,完成吊装。
3施工质量保证措施
3.1钢筋网片对接保证措施
钢筋网片加工时,将两段钢筋网片同时摆放在加工平台上,一同制作,纵筋一一对应,预留好搭接焊长度,形成一幅整体笼,在吊装焊接时便于操作,防止因加工钢筋网片尺寸不一,造成相互对接不上的情況发生。钢筋网片焊接时,每面两人先将四角钢筋绑扎焊接好,再焊接中间纵筋。钢筋工辅助将其它接头绑扎调整好,便于焊工操作,加快焊接进程。6米的钢筋网片,接头共有82个,按每人每小时7个接头,大概3~4个小时完成,可以满足施工要求。
钢筋网片纵向主筋焊接完成后,须补齐横向分布筋,并将焊渣一一敲除,质检、监理工程师对焊接接头的焊缝长度、质量检查合格后方能进行钢筋网片的吊装。
3.2防止槽壁坍塌措施
由于部分槽段钢筋网片需要进行对接,对接作业时间长达4个小时,加上钢筋网片起吊、对位,等待混凝土到场,因此槽段在完成清孔后将等待约6个小时之久,对泥浆护壁的效果提出了很高的要求。为保证清孔后槽段的安全,工程采用以下措施:
(1)选用优质膨润土制浆,比常规泥浆提高一个档次,并将泥浆比重适当调大至1.1g/cm3,确保槽段护壁质量;
(2)选用小型泥砂分离器进行清槽(图10);
(3)在钢筋网片焊接时严禁机械、车辆通过,防止挤压造成塌槽;
(4)钢筋网片整体下放后,对槽底沉渣重新进行测量,若不满足沉渣厚度要求须进行泥浆置换循环。
4结论
高压电缆下进行连续墙钢筋网片的吊装作业存在着较大的安全风险,高强度的对接和焊接对质量和安全风险都较大。在此特殊工况下,如何保证工程安全及质量的管理经验,希望本文可以给同行们一些借鉴。