第三航务工程局第二工程处在宝钢原料码头引桥墩台施工时,打破过去传统的老施工方法,在墩台大梁上采用了能适应长江口风大流急的施工条件,机械化施工程度高、速度快并能节省大量木材的大型吊挂式钢模。同时也成功地采用了预制钢筋骨架,水上混凝土搅拌船泵送混凝土施工等新工艺。现把钢模结构、制作与安装、技术经济效果说明如下:
In the construction of the bridge pier and pier at Baosteel Raw Material Terminal, the Second Engineering Department of the Third Navigation Engineering Bureau broke the traditional old construction methods and adopted the construction conditions on the pier and girder that can adapt to the heavy current of the Yangtze River. The mechanization construction level is high, Large suspended steel molds that are fast and save a lot of wood. At the same time, we also succeeded in using new technologies such as prefabricated reinforced steel frame and concrete pump for concrete construction. Now the steel structure, production and installation, technical and economic results are described below: