马田煤矿新星井由我公司第一工程处负责施工。主、副立井井筒在完成凿井吊挂准备及井颈段施工后,连续三个月分别累计成井165.8米和154.3米,平均月成井53米。我公司首次在两个井筒同时施工,利用整体金属模板浇灌混凝土井壁,掘砌工效分别达到1.26米~3/工日和1米~3/工日,比国家定额提高了27%和98%,经甲方验收,评定为优良品,下面谈谈我们的体会和认识。
Ma Tian mine star wells by the company I responsible for the construction of the first Agency. After completing the preparation of the shaft sinking and the construction of the wellbore and neck sections, the main shaft and the shaft of the auxiliary shaft have accumulated a total of 165.8 meters and 154.3 meters respectively for three consecutive months with an average monthly formation of 53 meters. For the first time in our company, the two wellbores are constructed at the same time. The whole metal formwork is used to irrigate the concrete shaft wall, and the work efficiency of digging is 1.26m ~ 3 / day and 1m ~ 3 / day respectively, which is 27% and 98% , By the acceptance of Party A, assessed as good, here to talk about our experience and understanding.