7404综采工作面是邢煤第一个综采工作面,其拆除工作经过了详细地计划,认真地组织取得了比较理想的效果。自第一架开始拆除,到最后一架安放在存放地点历时25天,总用工2316个,平均每架用工36.18个,每天完成2.56架。 在整个拆除过程中,速度是极不平衡的。第一架的试拆,由于运输条件限制,用工高达91个;而当运输条件调整得比较正常,工作效率发挥得比较充分的时侯,日拆达7架,平均每架用工为15.24个,其中54组支架是在白天内完成的,平均每天3架。显然,讨论在整个过程中如何发挥正常效率的问题,是有意义的。
7404 fully mechanized mining face is the first fully mechanized coal face in Xing Coal, the demolition work through a detailed plan, carefully organized and achieved a more satisfactory results. Since the first one began to be demolished, the last one was placed in a storage place for 25 days, with a total of 2316 workers, with an average of 36.18 workers. Each day, 2.56 aircraft were completed. Throughout the demolition process, the speed is extremely uneven. The first test-and-demolition, due to transport constraints, the labor up to 91; and when the transport conditions are more normal, work efficiency to play a more adequate Hou, Japan dismantled up to 7, an average of 15.24 for each job, Of these, 54 were completed during the day, an average of three daily. Obviously, it is significant to discuss the issue of how to achieve normal efficiency throughout the process.