论文部分内容阅读
上钢五厂转炉炉衬工段创造了转炉快速砌炉和快速拆炉的经验。使停炉到开炉的时间由原需的50~60小时缩短到22小时,其主要的经验为: (1)快速砌炉: 1)劳动组织的改善: 两个砌炉组集中力量砌一只炉,采取“休人不休马”的工作方法,解决了劳动力不平衡的现象,另外,根据每个人的体力进行适当的安排,使充分发挥每个人的作用,开工之前做好一切准备工作,消除停工待料,提高劳动生产率。因此使砌炉时间由原来12小时缩短为49分钟。
On the steel plant five converter plant lining section has created a converter fast build furnace and quick disassemble experience. The main experience is as follows: (1) Quickly building furnaces: 1) Improvement of labor organization: Two groups of building blocks concentrate their efforts to build one Only furnace, to take a “Hugh Rest never work” method of work to solve the phenomenon of labor imbalances, in addition, according to each person’s physical strength to make the appropriate arrangements to make full use of everyone’s role, before starting to do all the preparatory work, Eliminate work stoppages and improve labor productivity. Therefore, the time to build the furnace reduced from 12 hours to 49 minutes.