我厂现有28m~2小高炉两座,红旗3~#焦炉两组,配有选矿和土烧结,高炉、焦炉每天约有99800m~3剩余煤气空排,污染大气。一九七八年以来,我们重点搞了利用高炉、焦炉剩余煤气进行发电的工程。我厂当时两个矛盾都非常突出:一是生产要上去,但电力供应不足;二是大量煤气空排未能加以利用,且污染大气。仅以七八年为例:全厂停电169次,累计787小时。因停电少产生铁六千多吨,多耗用焦炭三千多吨。八项经济指标很不理想。焦炉、高炉及运转设备的寿命均有很大影响;公害的赔偿费逐年增加,给农民和国家都带来很大损失。为了解决这个问题,我们经过调查研究分析之后决定以煤气为燃料,搞1500千瓦机组的余热发电,在上级领导支持下,很快将睢宁电厂停用后一套汽轮发电机组和一台10T/小时水管式锅炉调拨给了我厂。搞余热发电,工程质量要求高,我们技术力量薄弱,缺乏经验,困难确实不少。为此,我们成立了余热发电工程指挥部和其他
Our factory has two existing 28m ~ 2 small blast furnaces, two sets of red flags 3 ~ # coke oven, with beneficiation and soil sintering, blast furnace, coke oven every day about 99800m ~ 3 remaining gas empty row, polluting the atmosphere. Since 1978, we have focused on projects that utilize the remaining gas from blast furnaces and coke ovens to generate electricity. At the time, two contradictions of our factory were very prominent: first, production went up but power supply was insufficient; second, a large amount of gas empty row failed to be utilized and polluted the atmosphere. Only seven or eight years for example: the whole plant 169 blackouts, a total of 787 hours. Due to power outages less than six thousand tons of iron, more consumption of more than 3,000 tons of coke. Eight economic indicators are not ideal. Coke oven, blast furnace and operating equipment have a great impact on the life; compensation for pollution increased year by year, to farmers and countries have caused great losses. In order to solve this problem, after investigation and analysis, we decided to use gas as fuel to engage in 1,500-kilowatt units of waste heat power generation, with the support of their superiors, Su Ning soon after the shutdown of a turbine generator set and a 10T / Hour water tube boiler allocated to my factory. Engage in waste heat power generation, high engineering quality requirements, our weak technical strength, lack of experience, a lot of difficulties indeed. To this end, we have set up a Waste Heat Power Generation Engineering Command and others