磨溪气田80×104m3/d装置经过9.5个月的试运行,现已正式通过验收,本文对该工艺装置(脱硫、脱水、回收)的试运状况进行了总结,同时对装置特点及存在问题进行了评析。尤其是1.2.3级组合冷凝冷却器在三个月内腐蚀报废值得我们思考。
The trial operation of 80 × 104m3 / d plant in Moxi Gas Field after 9.5 months has been formally approved. This paper summarizes the commissioning conditions of the plant (desulfurization, dehydration and recovery) Problems have been evaluated. In particular, 1.2.3 combination of condensing cooler corrosion scrap within three months worth our consideration.