1990年年省厅下达了修建烟威公路的计划,设计标准为全封闭、全立交式的一级汽车专用公路,这对我们来说是第一次。根据上级要求标准高、时间短的特点,我们首先对施工组织形式进行了研究。按照全国各地修建高等级路对外招标的形式,这显然是一个比较好的经验,但根据省里对这条路的控制投资和我们的实际情况,对外招标还有一定困难,研究的结果是,组织我们公路内部的力量,装备自己的队伍,实行内部承包、外部管理的办法组织施工。
In 1990, the provincial government department issued a plan to build the Yanwei Highway. The design standard is a totally enclosed and all-grade first-grade automobile highway. This is the first time for us. According to the higher requirements of standard high, short time characteristics, we first conducted a study on the construction organization. In accordance with the form of bidding for building high-grade roads across the country, this is obviously a relatively good experience. However, according to the control investment in this province and our actual situation, there is still some difficulty in inviting foreign bidders. As a result of the study, Organize the strength of our internal roads, equip our own teams, and implement internal contracting and external management to organize construction.