历时半年多,克服夏季高温、冬季严寒、天窗不足、时间紧、任务重等困难,实用天窗152个,安全、优质完成了青阜线36.5KM换枕、中修、大抬道“三同步”扩能改造任务,大幅提升了管内二通道的轨道承载能力和设备质量,为确保煤运通道的安全、畅通奠定了基础,为煤运通道运能进一步扩充创造了条件,也为直管体制下设备管理单位如何与修理单位优势互补、实现双赢、加快改造步伐积累了经验。
It took more than six months to overcome the difficulties of the summer high temperature, the winter cold, lack of skylights, tight schedule and heavy tasks. 152 utility skylights were completed safely and with high quality. "Capacity expansion and transformation tasks have greatly enhanced the orbital carrying capacity and quality of the two channels in the pipeline and laid the foundation for ensuring the safety and smoothness of the coal transport corridors and created the conditions for the further expansion of the coal transport corridors. Under the equipment management unit and the repair unit complement each other to achieve win-win situation and accelerate the pace of transformation has accumulated experience.