我厂1979年建成一条向高压微震造型生产线过渡的生产铸钢件震击造型生产线。此线的浇注段和3吨电弧炉放在一跨内。以往都是用行车浇注,这样阻碍了其它工序的正常生产。因此,我们在浇注段自行设计、制造了一台与3吨电弧炉配套使用的6吨座包浇注车。经实际试用,运行情况良好。一、设计依据目前国外(日、法)有的铸钢造型生产线采用了台车浇注形式。浇包安置在专门设置的桥
I plant in 1979 to build a high-pressure microseismic modeling production line transition production of castings shock modeling production line. This line casting section and 3 tons arc furnace on a cross. In the past are pouring traffic, this hindered the normal operation of other processes. As a result, we designed and built a 6-ton truck with a 3-ton electric arc furnace at the casting section. After the actual trial, running in good condition. First, the design basis At present, foreign (Japan, France) and some cast steel molding production line using trolley pouring form. Ladle placed on a specially set bridge