为扭转江垭枢纽引水发电系统施工初期严重滞后的被动局面 ,业主充分发挥工程建设的主导作用 ,合理调整施工进度计划 ,以关键路径为导向 ,制定切实可行的阶段目标 ,实行目标管理 ,严格控制关键项目工期。为了解决施工现场的矛盾 ,业主决定采取在施工现场召开协调会的方式 ,研究解决施工中出现的各种矛盾或技术问题 ,当天的问题当天解决 ,决不拖沓 ,大大提高了工作效率。同时也增加了业主、监理、设计与承包商之间的沟通和联系。为顺利实现江垭水利枢纽工程提前发电目标起到了积极的推动作用
In order to reverse the passive situation of serious lag in the early stage of water diversion and power generation system construction of Jiangya Hydropower Station, the owners give full play to the leading role of engineering construction, adjust the construction schedule rationally, take the key path as the guide, formulate practical stage targets, implement target management and strictly control Key project duration. In order to solve the contradiction on the construction site, the owners decided to adopt a coordination meeting held on the construction site to study and solve all kinds of contradictions or technical problems that occurred during the construction. The problems of the day were solved on the same day, and procrastination was never carried out. As a result, the work efficiency was greatly improved. At the same time also increased the owners, supervisors, design and communication between contractors and contacts. It has played a positive role in promoting the goal of generating electricity ahead of Jiangya Water Control Project