由中交二公局第三工程有限公司承建的宿新高速公路路面工程SX-22合同段位于宿新高速公路中段,起点桩号K19+450、终点桩号K39+700,全长20.25km,合同工期18个月。宿新22标项目于2011年6月底正式组建,进场后仅用了13天时间严格按照标准化要求完成了经理部临建任务并于7月13日入住办公,15天变压器安装到位并开始安装调试水稳拌合设施,20天时间拌和设备安装完成并
SX-22 Contract Section of Suxin Expressway Pavement Construction undertaken by CCCC Third Engineering Co., Ltd. is located in the middle section of Su-Xin Expressway with starting stake K19 + 450, ending stake K39 + 700, total length 20.25km, Contract duration 18 months. Su-22 new standard project was officially established by the end of June 2011, only 13 days after entering the site in strict accordance with the requirements of the standardization of the Ministry completed the temporary construction tasks and stay in the office on July 13, 15-day transformer installed in place and began to install Debug water stable mixing facilities, 20 days to complete the mixing equipment installation and