论文部分内容阅读
我矿的采矿、剥离量,过去都是以生产鉴量为准。由于计量不准确,日积月累误差很大。1962年的计量数字与测量验收相差9%。自从去年冶金部指示矿山生产产量与工程量均以测量验收数字为准以后,我们曾多次研究改进了测量验收工作方法,因此去年的测量验收数字与鉴量差只有0.55%,比1962年降低8.45%。现将测量验收的具体作法简介如下。(一)认真贯彻各项测量技术规程制度。
Mine mining, stripping the amount of production in the past are subject to the measure. Due to inaccurate measurement, accumulated errors over time. 1962 measurement and acceptance of a difference of 9%. Since the Ministry of Metallurgical instructed mine production and construction volume last year that the measurement and acceptance figures prevail, we have conducted many studies to improve the measurement and acceptance work methods. As a result, the survey acceptance figures and measurement differences last year were only 0.55%, lower than those in 1962 8.45%. Now the measurement of acceptance of the specific practices are as follows. (A) conscientiously implement the measurement of technical regulations system.