1991年4月18日国务院批准1991年新开工大中型项目56项,其中水电项目3项。珠江流域上游南盘江上的天生桥一级水电站是其中一项,该项目装机容量120万kW,年发电量53.8亿kW·h,调节性能较好。由于一级电站水库调节.将增加下游梯级水电站发电量21.9亿kW·h。目前该电站水、电、路等三通一平工作正紧张进行,预计1994年截流,主体工程采取招标方式承建,计划1998年第1台机组并网发电。该项目为中央与地方
On April 18, 1991, the State Council approved 56 large and medium-sized projects newly started in 1991, of which 3 were hydropower projects. The Tianshengqiao-1 hydropower station on the Nanpanjiang River in the upper reaches of the Pearl River Basin is one of the projects. The installed capacity of the project is 1.2 million kW and the annual power generation is 5.38 billion kW · h, so that the regulation performance is better. Due to the adjustment of a hydropower station, it will increase the generating capacity of downstream cascade hydropower stations by 2.19 billion kW · h. At present, the hydropower, electricity and road work of the power station is under intense work in the three links and one leveling. It is estimated that the main dam will be constructed by bidding in 1994 and the first unit planned to be connected to the grid in 1998. The project is central and local