接受一项吊装工程,首先要合理选择起重机,确定最短的起重机吊杆长度。我们经过长期摸索,找到了一个简单而快速的计算方法——“加七加八法”。当遇到柱间距为6米的厂房结构吊装工程时,只要把厂房结构最高点的标高,加上现场地面低于设计标高的差值,得出要求吊装结构的高度后,再加上7米或8米,就是能满足吊装要求的起重机最短吊杆长度。如此简单而快速的方法,只要具有初小文化水平就能掌握,所以起重工亲切地称它为“加七加八法”。
To accept a hoisting project, we must first select a reasonable crane, determine the shortest crane boom length. After a long period of groping, we found a simple and fast method of calculation - “plus seven plus eight methods.” When encountering the workshop structure hoisting project with a column spacing of 6 meters, as long as the height of the highest point of the plant structure is added, plus the difference of the site ground below the design elevation, the height of the required lifting structure is added, plus 7 meters. Or 8 meters, is the shortest crane boom length that can meet the hoisting requirements. Such a simple and quick method can be grasped as long as it has a small initial cultural level. Therefore, the hoisting worker kindly calls it “plus seven plus eight”.