1978年我公司一工区第二施工队在11、12、13、14号4栋外砖内模统建宿舍工程上运用统筹法组织了流水施工,收到了良好效果。11、12、13号三栋为五层墩式楼,每栋面积1074平方米,14号是由三个单元组合的五层条式楼,面积2437平方米;四栋建筑面积共5659平方米。主体工期45天,±0以上84天全部竣工。工程质量全部为优良品,未发生重大安全事故,土建现场施工单方用工2.28工日/米~2,劳动效率平均达到110%以上,节约水泥26吨,降低成本5.96%。
In 1978, the second construction team of our company’s first-class construction area used the unified method to organize water-flow construction on the externally-built four-block internal structure dormitory projects No. 11, 12, 13, and 14 and received good results. The No.11, No.12 and No.13 buildings are five-story pier buildings with an area of 1,074 square meters. The No.14 is a five-story building with three units and an area of 2,437 square meters. The four buildings have a total area of 5,659 square meters. . The duration of the main project is 45 days, and it is completed within ±0 days and 84 days. The quality of the project was all excellent products. There was no major safety accident. The civil construction site had unilaterally employed 2.28 labor days/m~2, and the labor efficiency averaged over 110%, saving 26 tons of cement and reducing costs by 5.96%.