对测量项目的报价,通常是根据项目的实物工程量和定额单价计算项目的费用,或者将项目的实物工程量根据定额转换成定额标准工作量以计算费用。由于测量中心的服务期是按年计,能界定其工作内容,但不能计算其工作量;测量中心是长驻机构,无论有无工作,设备和人员必须长驻现场。这两大难题,用前述方法不能准确、全面、科学地计算中心项目费用。在某电站测量中心投标报价中,采用了实物法报价,最终投标的结果证明了该方法计算的报价在该类项目中的可行性。
The price quoted for the measurement items is usually calculated according to the actual amount of the project and the fixed unit price, or the actual amount of the project is converted into a fixed standard workload according to the quota to calculate the cost. Since the service life of a measurement center is calculated on an annual basis, the work content can be defined, but the workload can not be calculated. The measurement center is a permanent agency, and the equipment and personnel must stay on site with or without work. These two major problems, using the aforementioned method can not accurately, comprehensively and scientifically calculate the center project costs. In a bidding quotation of a power station measurement center, the quotation of the in-kind method is adopted. The result of the final bidding proves the feasibility of the quoted price calculated by the method in such a project.