我厂鉴于电力工业发展露天锅炉的需要,不久前曾对国内某几台露天锅炉的运行情况进行了一次调查。关于露天锅炉基建投资、运行等方面的经济性,华东电力设计院等单位在几年前已作了详细调查,而这次调查时间比较短促,因此在博山和南定两电厂我们着重对露天锅炉的“五防”问题进行了现场调查研究,其中博山370电厂是调查的重点。兹将调查的结果扼要介绍如下,作为一种情况交流,提供有关部门参考。
In view of the needs of open-air boilers in the electric power industry, I recently conducted a survey on the operation of some open-air boilers in China. On the open-air boiler infrastructure investment, operation and other aspects of economy, East China Electric Power Design Institute and other units in a few years ago have made a detailed investigation, and the survey time is relatively short, so Boshan and Nanding two power plants we focus on the open Boiler “five defenses” conducted a field investigation of the issue, which Boshan 370 power plant is the focus of the investigation. The results of the survey will be briefly described below, as a kind of exchange of information, to provide relevant departments for reference.