摘要:因为复杂工程施工具有不确定性地网络设计特点,再加上传统、老旧的施工管理技术同样不能直观、形象地展现出大型桥梁整体的施工进度,所以应把4D的可视化动态技术广泛应用到桥梁建设、管理工作中。本文围绕复杂桥梁工程加以分析,得出结论如下:动态可视化系统在一定程度上可以预计工程的整体进度跟资源使用的实时情况;还能计算出工程周期、施工计划、重点桥梁路段以及成本、质量等。
关键词:三维动态仿真;不确定;子系统;模型库
Abstract: because of complicated engineering construction is uncertain to network design features, plus the traditional, old construction management technology also can't intuitive, image to show a large bridge whole construction progress, so should put 4 D visualization of dynamic technology is widely applied to building Bridges, management work. This paper focus on complex to analyze the bridge engineering, draw the conclusion is as follows: dynamic visual system in some extent could project is expected to the whole progress of real-time situation with the use of resources; Also can calculate project cycle, construction plan, key road and bridge cost, quality, etc.
Keywords: 3 d dynamic simulation; Not sure; Subsystem; Model library
中图分类号:K928.78文献标识码:A 文章编号:
目前,应用计算机网络动态模拟技术达到工程施工建设的数字信息化、可视化以及智能化的目标早已成为建筑业未来的发展任务。现阶段,工程施工可视化的动态仿真技术分析及多媒体工程管理信息技术体系通常强调以下几点:(1)在复杂桥梁、结构进行施工时的受力模拟仿真;(2)针对公路、铁路以及各桥梁、隧道进行三维魔方呈现;(3)项目工程管理运作信息体系;(4)施工项目在施工环节中的三维动态可视仿真。
现阶段,应用最为广泛的,时间最早的仿真网络技术就是循环模式的。目前国内针对工程施工在仿真技术方面的研究主要被广泛应用于水利部门,但把这种系统仿真网络技术应用到公路、铁路等类型的复杂建筑物项目施工进程里还是处在研究性的试探阶段。想要让大型桥梁在施工运作中使用4D仿真模拟技术,就必须要深入研制不确定型的计算机网络计划跟动态化的工程施工仿真体系。围绕这一话题,针对复杂桥梁在施工过程里的动态可视化进行仿真模拟进行探讨。
1、简单介绍不确定型的多媒体网络设计的工期跟模拟的费用
大型复杂性的桥梁在施工时所需耗用的周期偏长,总体需要投入的资源量也比较大,施工的工期以及所需资源等具体数值都是不可确定型的。由此可知,想要模拟出复杂桥梁整体的施工进程跟具体成本费用,就必须要关键研究不确定型的可视化网络技术体系。在前期,通常选择“计划评审法”这一模式来仿真模拟不确定型的动态化网络技术。“计划评审法”一般估算3方面,第一、工序施工周期最乐观的数值a,第二最大可能性的数值m,第三最悲观的数值b,利用(a+4m+b)/6这一公式来计算出各工序实际的持续时间,再遵循关键线路法原则计算总工期。通常“计划评审法”算出来的计算结果都较小,方差过大,换句话讲,就是说计算结果整体的可靠度不高。用模拟仿真技术深入探讨不确定性质的网络可视化系统,步骤安排具体如下所述:
(1)判断资源是否受到束缚、限制,进而明确各项目工序能施工的最快时间点;
(2)高效利用蒙特卡洛模式,精确性地仿真计算出每一项目工序的长久性持续时间跟实际成本费用;
(3)依照规划的工序次序,完成复杂性项目工程仿真可视化的不确定型动态技术。
2、探讨复杂桥梁工程施工时的动态可视化技术
2.1可视化系统功能构成模块
所谓的“工程施工可视化系统功能构成模块”通常由复杂桥梁4D施工建设模型、不确定性质的网络模拟仿真系统、工程施工3维动态可视化演示以及各查询体系仿真模拟成果導出这4个程序组织而成的,在这四个系统里面,不确定性质的网络模拟仿真系统跟工程施工3维动态可视化演示其实就是“工程施工可视化系统功能构成模块”里最核心的项目技术。
2.1.1复杂桥梁4D施工建设模型
所有复杂性质的桥梁通常都是将标准构件跟最基本性的构件结合在一起。在系统的标准数据资源库里含有大量的有关标准构件尺寸的信息资源,用户可以有选择性的修改、利用这些数据。而针对最基本性的构件来说,通常是用户将设计好的尺寸输进去,建立起一道最基础构件的数据库模型。另一方面,不但要建立起三维的构件模型,还要描绘出跟各种构件相联系的模型进程数据跟资源性质,进而更加高效性地生成项目施工系统4D仿真技术跟信息资源数据库模型。
2.1.2不确定性质的网络模拟仿真系统
按照不同构件设计、规划的施工进度数据跟和资源实际性质,生成最基础、原始的网络形式规划步骤,凭借蒙特卡洛法仿真模拟计算这一不确定性质的网络规划数据,从中合理运用公式计算出具体的各道工序最佳动工时间段,进一步模拟出最接近实际的施工设计规划。并按照模拟所得的进度成果跟成本费用情况来更换之前基础构件所计划的施工进程跟费用成本资源数据。
2.1.3工程施工3维动态可视化演示以及各查询体系
可以通过模拟实际项目施工的进程管理来得出复杂桥梁的施工3D动画程序,并在一定基础上,实时显示出大型桥梁各基础性质的构件在施工作业时的具体信息跟数据属性。这一动态演示程序就能让桥梁3D模型直接围绕X,y,z轴进行任意角度的旋转、缩放,在一定程度上改变整个视觉接触点的方位跟观察角度、方向以及透视性质的显示用途。所使用的查询方法通常包括了基本条件查询跟动态的可视化查询等。所谓的“基本条件”查询指的就是满足用户基本要求,有针对性地查询项目施工的属性特征跟工程设计的图纸;而动态的可视化查询指的就是在三维动态图形规划下,有着力点地点下基础性的构件来超找施工项目进程跟具体数据信息资源。
2.1.4仿真模拟成果导出
这一子系统在一定程度上可以将仿真模拟的最终成果导出来:施工项目周期、具体的进度规划流程、关键路线以及各信息资源实时的使用情况,还能呢个计算并优化出最高效的横道图、信息资源柱状图等,并根据图得出文本文档,再进行打印预览、扫描等各个用途。
2.2系统信息数据库
整个系统都要求利用管理仿真模型里面提及的参数值、模型方法以及计算公式。由此可知,应尽快对数据库技术实施仿真模型方法。这里的系统信息数据库主要由数据资源库、模型数据库、方法数据库。
2.2.1数据资源库
(1)通常情况下,通常包罗了一切项目施工所要利用到的信息数据,就像复杂桥梁的具体尺寸、成本费用数值等。
(2)项目各项工序周期数据资源库。通常用到的就是计算得出的工序完成具体时间跟统计所需的参考数值。
(3)对项目工程进行类比所用的数据资源库。在计算机中输入跟工程项目相类似的原始资料,简单建立起类比工程的信息库,从规模、各道工序、施工模式、具体进度等各个方面展开比较、探讨,进而为专业技术人员在项目的研究过程中提供决策的凭证。
2.2.2模型数据库
各种工序模型通常有平行化的、顺序化的、浇筑形式的、土石填筑模式的施工建筑模型;而单元模型就是节点、复合形式节点以及排队节点等模型数据库。
2.2.3方法数据库
对施工进行可视化的动态仿真来讲,常用的算法一般有平行施工计算模式、顺序施工计算模式跟蒙特卡洛动态仿真计算方法之类的;深入解析探讨的算法一般有调查施工实际进程的计算模式、换算日常时期的计算模式、查找关键路线的计算、详细统计施工力度的计算模式以及判别高峰施工阶段的计算模式之类的。
3、结语
综上所述,可知:
(1)明确在资源受到制约的条件下,如何准确计算出工序特征耗用时长,对那些不确定的动态网络设计展开仿真模拟实验。
(2)将桥梁3D仿真模型跟实际施工项目进程计划、资源力度联合起来,建设为桥梁施工实际进度跟费用资源管制的4D网络模型,凭借3维模型来强调出整个复杂桥梁项目施工的详细步骤,这样做的话,才能描绘出整个重大工程动态化的施工程序跟查询状态、资源管理等属性数据。
(3)围绕施工实际进度跟优化、整合资源系统来讲,急需专家进一步深入调研、探索。
参考文献:
[1] 刘晓明,罗周全,孟稳权,张保,王国焘. 深井采场大规模垮塌三维探测及可视化计算[J]. 中南大学学报(自然科学版), 2011,(01) .
[2] 杨丽,胡云峰. 桥梁工程外观质量的施工控制[J]. 中国新技术新产品, 2010,(18) .
注:文章内所有公式及图表请用PDF形式查看。
关键词:三维动态仿真;不确定;子系统;模型库
Abstract: because of complicated engineering construction is uncertain to network design features, plus the traditional, old construction management technology also can't intuitive, image to show a large bridge whole construction progress, so should put 4 D visualization of dynamic technology is widely applied to building Bridges, management work. This paper focus on complex to analyze the bridge engineering, draw the conclusion is as follows: dynamic visual system in some extent could project is expected to the whole progress of real-time situation with the use of resources; Also can calculate project cycle, construction plan, key road and bridge cost, quality, etc.
Keywords: 3 d dynamic simulation; Not sure; Subsystem; Model library
中图分类号:K928.78文献标识码:A 文章编号:
目前,应用计算机网络动态模拟技术达到工程施工建设的数字信息化、可视化以及智能化的目标早已成为建筑业未来的发展任务。现阶段,工程施工可视化的动态仿真技术分析及多媒体工程管理信息技术体系通常强调以下几点:(1)在复杂桥梁、结构进行施工时的受力模拟仿真;(2)针对公路、铁路以及各桥梁、隧道进行三维魔方呈现;(3)项目工程管理运作信息体系;(4)施工项目在施工环节中的三维动态可视仿真。
现阶段,应用最为广泛的,时间最早的仿真网络技术就是循环模式的。目前国内针对工程施工在仿真技术方面的研究主要被广泛应用于水利部门,但把这种系统仿真网络技术应用到公路、铁路等类型的复杂建筑物项目施工进程里还是处在研究性的试探阶段。想要让大型桥梁在施工运作中使用4D仿真模拟技术,就必须要深入研制不确定型的计算机网络计划跟动态化的工程施工仿真体系。围绕这一话题,针对复杂桥梁在施工过程里的动态可视化进行仿真模拟进行探讨。
1、简单介绍不确定型的多媒体网络设计的工期跟模拟的费用
大型复杂性的桥梁在施工时所需耗用的周期偏长,总体需要投入的资源量也比较大,施工的工期以及所需资源等具体数值都是不可确定型的。由此可知,想要模拟出复杂桥梁整体的施工进程跟具体成本费用,就必须要关键研究不确定型的可视化网络技术体系。在前期,通常选择“计划评审法”这一模式来仿真模拟不确定型的动态化网络技术。“计划评审法”一般估算3方面,第一、工序施工周期最乐观的数值a,第二最大可能性的数值m,第三最悲观的数值b,利用(a+4m+b)/6这一公式来计算出各工序实际的持续时间,再遵循关键线路法原则计算总工期。通常“计划评审法”算出来的计算结果都较小,方差过大,换句话讲,就是说计算结果整体的可靠度不高。用模拟仿真技术深入探讨不确定性质的网络可视化系统,步骤安排具体如下所述:
(1)判断资源是否受到束缚、限制,进而明确各项目工序能施工的最快时间点;
(2)高效利用蒙特卡洛模式,精确性地仿真计算出每一项目工序的长久性持续时间跟实际成本费用;
(3)依照规划的工序次序,完成复杂性项目工程仿真可视化的不确定型动态技术。
2、探讨复杂桥梁工程施工时的动态可视化技术
2.1可视化系统功能构成模块
所谓的“工程施工可视化系统功能构成模块”通常由复杂桥梁4D施工建设模型、不确定性质的网络模拟仿真系统、工程施工3维动态可视化演示以及各查询体系仿真模拟成果導出这4个程序组织而成的,在这四个系统里面,不确定性质的网络模拟仿真系统跟工程施工3维动态可视化演示其实就是“工程施工可视化系统功能构成模块”里最核心的项目技术。
2.1.1复杂桥梁4D施工建设模型
所有复杂性质的桥梁通常都是将标准构件跟最基本性的构件结合在一起。在系统的标准数据资源库里含有大量的有关标准构件尺寸的信息资源,用户可以有选择性的修改、利用这些数据。而针对最基本性的构件来说,通常是用户将设计好的尺寸输进去,建立起一道最基础构件的数据库模型。另一方面,不但要建立起三维的构件模型,还要描绘出跟各种构件相联系的模型进程数据跟资源性质,进而更加高效性地生成项目施工系统4D仿真技术跟信息资源数据库模型。
2.1.2不确定性质的网络模拟仿真系统
按照不同构件设计、规划的施工进度数据跟和资源实际性质,生成最基础、原始的网络形式规划步骤,凭借蒙特卡洛法仿真模拟计算这一不确定性质的网络规划数据,从中合理运用公式计算出具体的各道工序最佳动工时间段,进一步模拟出最接近实际的施工设计规划。并按照模拟所得的进度成果跟成本费用情况来更换之前基础构件所计划的施工进程跟费用成本资源数据。
2.1.3工程施工3维动态可视化演示以及各查询体系
可以通过模拟实际项目施工的进程管理来得出复杂桥梁的施工3D动画程序,并在一定基础上,实时显示出大型桥梁各基础性质的构件在施工作业时的具体信息跟数据属性。这一动态演示程序就能让桥梁3D模型直接围绕X,y,z轴进行任意角度的旋转、缩放,在一定程度上改变整个视觉接触点的方位跟观察角度、方向以及透视性质的显示用途。所使用的查询方法通常包括了基本条件查询跟动态的可视化查询等。所谓的“基本条件”查询指的就是满足用户基本要求,有针对性地查询项目施工的属性特征跟工程设计的图纸;而动态的可视化查询指的就是在三维动态图形规划下,有着力点地点下基础性的构件来超找施工项目进程跟具体数据信息资源。
2.1.4仿真模拟成果导出
这一子系统在一定程度上可以将仿真模拟的最终成果导出来:施工项目周期、具体的进度规划流程、关键路线以及各信息资源实时的使用情况,还能呢个计算并优化出最高效的横道图、信息资源柱状图等,并根据图得出文本文档,再进行打印预览、扫描等各个用途。
2.2系统信息数据库
整个系统都要求利用管理仿真模型里面提及的参数值、模型方法以及计算公式。由此可知,应尽快对数据库技术实施仿真模型方法。这里的系统信息数据库主要由数据资源库、模型数据库、方法数据库。
2.2.1数据资源库
(1)通常情况下,通常包罗了一切项目施工所要利用到的信息数据,就像复杂桥梁的具体尺寸、成本费用数值等。
(2)项目各项工序周期数据资源库。通常用到的就是计算得出的工序完成具体时间跟统计所需的参考数值。
(3)对项目工程进行类比所用的数据资源库。在计算机中输入跟工程项目相类似的原始资料,简单建立起类比工程的信息库,从规模、各道工序、施工模式、具体进度等各个方面展开比较、探讨,进而为专业技术人员在项目的研究过程中提供决策的凭证。
2.2.2模型数据库
各种工序模型通常有平行化的、顺序化的、浇筑形式的、土石填筑模式的施工建筑模型;而单元模型就是节点、复合形式节点以及排队节点等模型数据库。
2.2.3方法数据库
对施工进行可视化的动态仿真来讲,常用的算法一般有平行施工计算模式、顺序施工计算模式跟蒙特卡洛动态仿真计算方法之类的;深入解析探讨的算法一般有调查施工实际进程的计算模式、换算日常时期的计算模式、查找关键路线的计算、详细统计施工力度的计算模式以及判别高峰施工阶段的计算模式之类的。
3、结语
综上所述,可知:
(1)明确在资源受到制约的条件下,如何准确计算出工序特征耗用时长,对那些不确定的动态网络设计展开仿真模拟实验。
(2)将桥梁3D仿真模型跟实际施工项目进程计划、资源力度联合起来,建设为桥梁施工实际进度跟费用资源管制的4D网络模型,凭借3维模型来强调出整个复杂桥梁项目施工的详细步骤,这样做的话,才能描绘出整个重大工程动态化的施工程序跟查询状态、资源管理等属性数据。
(3)围绕施工实际进度跟优化、整合资源系统来讲,急需专家进一步深入调研、探索。