超过索赔时限,承包人并不必然丧失索赔权利工程索赔是指在合同履行过程中,对于并非自己一方的过错,而是应由对方承担责任的情况造成的损失,向对方提出工期顺延和经济补偿的要求。工程索赔的时限是指各类标准施工合同通用条款中规定的,或者是承发包双方在施工合同中约定的提出索赔的时间限制。《建设工程施工合同1999年示范文本》第36.2条,规定的索赔时限是28天。《标准施工招标文件2007年版》第23.1条,规定的索赔时限也是28天,同时,还进一步规定,承包人未在28天内提出索赔请求的,即丧失要求追加付款和延长工期的权利。
Exceed the time limit for claim, the contractor does not necessarily lose the right to claim the project claims refers to the performance of the contract, not for their own fault on the one hand, but by the other party to bear the responsibility of the situation caused by the loss, to the other party to postpone the duration and financial compensation Request. The time limit of engineering claim refers to the time limit stipulated in the general clauses of various standard construction contracts or the claims made by both parties in the construction contract. Article 36.2 of the “1999 Construction Model Construction Contract for Construction Contract” stipulates a time limit of 28 days. Article 23.1 of “Standard Construction Bidding Document 2007” also stipulates a time limit of 28 days. Meanwhile, it is further stipulated that if the claimant fails to file a claim within 28 days, it will lose the right to request additional payment and extend the construction period.