导流(泄洪)洞工程:除进水塔上部结构及尾水渠王文成沟临时导流渠段未完外,其他工程全部完成,具备过流条件。大坝工程:大坝Ⅰ标段(0+700-2+700)全线达到111m高程,局部达到112m高程;大坝Ⅱ标段(2+700-4+150)段大坝土石方填筑全线达到97.0m以上高程,局部填筑112m高程;大坝Ⅲ标段(河槽段4+150-4+703)上游戗堤(除龙口段外)已填筑至94.0m高程右;大坝基础防渗标段左岸台地(3+725~4+242段)防渗墙及墙下帷幕灌浆已基本完成,右岸台地段地质复勘工作已完成,具备防渗墙施工条件。
Diversion (flood discharge) tunnel project: In addition to the upper structure of intake towers and tailings Wang Wencheng ditch temporary diversion channel is not completed, other projects are completed, with overcurrent conditions. Dam Project: The entire stretch of Ⅰ section of dam (0 + 700-2 + 700) reaches a height of 111m and reaches a partial elevation of 112m. For dam Ⅱ section (2 + 700-4 + 150) The elevation above 97.0m is filled with a partial elevation of 112m. The upstream embankment (except Longkou section) of the third section of the dam Ⅲ (channel 4 + 150-4 + 703) has been filled to an altitude of 94.0m. The dam foundation The seepage prevention wall and the curtain grouting in the wall of the left bank of the impermeable segment have been basically completed, and the geological reconnaissance work has been completed in the right bank section, with the construction conditions of the impervious wall.