针对模具制造过程的特点,在工件不同时到达的情况下,研究了前阶段带有成组约束的两阶段柔性同序加工车间的调度问题,建立了目标函数为最小化最大完成时间的调度数学模型.基于Potts的RJ′算法提出解决此类问题的启发式算法,并将该算法应用到轮胎模具企业的生产实例中,通过仿真说明数学模型和求解方法的可靠性和有效性.
According to the characteristics of the mold manufacturing process, the scheduling problem of the two-stage flexible same-order processing shop with group constraint in the previous stage is studied under the condition that the workpiece does not arrive at the same time. The scheduling mathematics with the objective function of minimizing the maximum completion time Model.The Potts-based RJ algorithm proposed a heuristic algorithm to solve such problems, and applied the algorithm to the production of tire mold enterprises, and demonstrated the reliability and effectiveness of the mathematical model and the solving method through simulation.