我公司5 000t/d生产线是四川灾后重建的重点项目,于2008年9月开工建设,2009年9月22日点火试生产,11月底通过验收。该生产线的主要工艺配置为:MLS4531立式生料磨、Φ4.8m×72m回转窑(配备新型CDC分解炉及双系列五级预热器)及两台并联Φ4.2m×13m水泥磨、辊压机及高效选粉机组成的联合粉磨系统。
My company 5000t / d production line is a key project of post-disaster reconstruction in Sichuan, started construction in September 2008, September 22, 2009 ignition pilot production, passed the acceptance by the end of November. The main process configuration of the production line: MLS4531 vertical raw mill, Φ4.8m × 72m rotary kiln (equipped with new CDC decomposition furnace and double series of five preheater) and two parallel Φ4.2m × 13m cement mill, roller Press and efficient separator consisting of a joint grinding system.