宁国水泥厂自去年九月下旬开工以来,建设速度快,工程质量好,圆满地完成了主攻基础和地下工程的第一个战役的任务。到目前为止,累计完成土石方90多万立方米;主工艺线地下基础工程近2万立方米混凝土已浇注完毕;整个基础已出地面4米多;日送水量2万立方米的输水工程已建成送水;铁路专用线已建成通车;一部分厂房和宿舍楼拔地而起;主工艺线工程优良品率达到98.2%。由于成绩显
Since the Ningguo Cement Plant started construction in late September last year, the construction speed is fast, the quality of the project is good, and the mission of the first battle of the main attack base and underground works has been successfully completed. So far, more than 900,000 cubic meters of earth and stone have been accumulated; nearly 20,000 cubic meters of concrete have been poured into the underground engineering of the main process line; the entire foundation has been out of the ground by more than 4 meters; the daily water delivery volume of 20,000 cubic meters has been The water supply was completed; the special railway line had been completed and opened to traffic; part of the factory buildings and dormitory buildings had been erected; the excellent product rate of the main process line project reached 98.2%. Due to significant results