据交通部西部地区通县公路建设办公室透露,截至2002年1月,西部通县油路项目工程可行性研究报告已基本完成,其中94个项目已开工,55个项目处于设计阶段,101个项目正在进行招投标工作。目前,西部通县油路工程已累计完成路基土石方7739.84万立方米,路面工程8593.68千平方米,完成投资39.95亿元,占计划投资的10.7%。预计到今年3月底,除西藏、新疆和黑龙江省由于受自然地理条件限制部分项目将推迟到5月份开工外,其余省(区、市)均可按计划完成各项前期准备工作,通县油路建设进展顺利。
According to the office of Tongxian Highway Construction in the western part of the Ministry of Communications, as of January 2002, the feasibility study report of the western Tongxian oil pipeline project has been basically completed. 94 projects have been started, 55 are in the design stage, 101 projects Bidding is underway. At present, the western Tong County oil pipeline project has completed a total of 77,398,400 cubic meters of roadbed earth and stone, road construction 8593.68 square meters, an investment of 3.955 billion yuan, accounting for 10.7% of planned investment. Expected to be the end of March this year, in addition to Tibet, Xinjiang and Heilongjiang Province due to natural and geographical conditions due to some of the projects will be postponed to start in May, the remaining provinces (autonomous regions and municipalities) can complete the preparatory work according to plan, Tongxian oil Road construction is progressing well.