一、概述为了解决小子溪水库(总库容470万立米,死库容40万立米)的防洪、检修和增加供水量等问题,在大坝右岸开凿了全长380米的引水隧洞。由于隧洞进水口位于水库死水位以下,而采用了水下岩塞爆破方案。78年1月21日,水下爆破成功,爆破效果较好,进水口成形尺寸基本符合设计要求;同时未衬砌隧洞无塌方,石渣顺利泄走,爆破振动对相距129米的土坝、闸门和相距250米的电站等水工建筑物没有产生任何破坏影响。
I. Overview In order to solve the problems of flood control, overhaul and water supply increase in Xiaoxi River Reservoir (total capacity of 4.7 million cubic meters and 400,000 cubic meters of dead storage capacity), a diversion tunnel with a total length of 380 meters was drilled on the right bank of the dam. As the tunnel inlet is below the level of the reservoir dead water, an underwater rockbolt blasting scheme is adopted. January 21, 78, the success of underwater blasting, blasting better, forming the size of the inlet basically meet the design requirements; at the same time without lining the tunnel without collapse, gravel smoothly drain, blasting vibration of 129 meters apart from the earth dam, gate And hydraulic structures such as hydropower stations within 250 meters of each other did not produce any destructive impact.