河北省沧州地区在1964年冬季的宣惠河疏浚工程中,打了一个胜仗。7.8万多名民工,施工35天,完成土方586万多立方米,为原设计冬季施工任务的2.4倍,为第一期工程任务的55%,为全部疏浚工程任务的45%。这就是说,原计划三年完成的任务,只要一个冬春就可以完成了。这项工程的投资(包括桥梁、涵洞、跌水等129座建筑物),最初规划为3,998万元,根据巳经进行的工作看,有1,400万元左右就够了,
Cangzhou, Hebei Province in the winter of 1964, Xuhui River dredging project, played a victorious battle. More than 78,000 migrant workers, 35 days of construction, completed more than 5.86 million cubic meters of earthwork, 2.4 times the original design of winter construction tasks, 55% of the first phase of the project and 45% of the total dredging tasks. This means that the task that was originally planned to be completed in three years can be completed in just one winter or spring. The project’s investment (including 129 bridges, culverts, water falls, etc.) was originally planned to be 39.98 million yuan. Based on the work already carried out, about 14 million yuan will be enough.