巷道下山掘进过程中,出矸一直是制约施工进度的难题。在一般施工过程中使用绞车牵引1.5t、3t矿车或者DSJ-80带式输送机出矸,巷道距离超过400m以后使用矿车出矸往返时间长,出矸效率低,难以满足快速施工要求。DSJ-80带式输送机在下山施工有水时不能正常使用。南一采区皮带斜井工程量1082m,坡度16°下山,正常涌水量0.38m3/min,传统的出矸方法难以满足巷道快速施工的要求,经过研究决定,在南一采区皮带斜井施工过程中使用自动卸载式箕斗出矸。
Roadway down the tunneling process, the gangue has been a constraint to the construction progress of the problem. In the general construction process using winch traction 1.5t, 3t tub or DSJ-80 belt conveyor gangue, roadway more than 400m from the car using a long time from the gangue, Gangue ineffective, difficult to meet the rapid construction requirements. DSJ-80 belt conveyor in the construction of water down can not be used normally. In the first mining zone, the amount of inclined shaft of the belt is 1082m, the gradient is 16 °, and the normal water inflow is 0.38m3 / min. The traditional method of rock discharge can hardly meet the requirements of rapid construction of the roadway. After research and decision, The process of using automatic unloading dump skip gangue.