论文部分内容阅读
我工区施工的崇文门东大街道路工程于一九七九年九月三十日完成,同时开放交通,但在一九八○年元月份就发现了大量裂缝,这一现象在过去是少见的,就我们的条件做了一些调查。并提出不成熟意见: 崇文门东大街道路工程全长约1.5公里。土方路基大部分在一九七八年底完成,道路结构层在一九七九年九月完成,其中路面是集中在七、八、九月份中完成,从施工的时间,季节看,都很好,道路结构设计也能满足通车要求,施工技术力量很强,放行时交通量很小,然而在不到半年有一半多的路段出现了大量的裂缝。现将裂缝,设计结构,
The construction of the Chongwenmen East Main Road in our work area was completed on September 30, 1979 and traffic was also liberalized. However, a large number of cracks were found in January 1980, a phenomenon rare in the past , Did some research on our conditions. And put forward an immature opinion: Chongwenmen East Avenue road project length of about 1.5 km. Most of the earthwork embankments were completed by the end of 1978, and the road structure was completed in September 1979. The road surface was completed in July, August and September, and the construction time and season were good , The road structure design can also meet the traffic requirements, construction technology is very strong, when the traffic release is small, but in less than half a year more than half of the road there have been a lot of cracks. Now cracks, design structure,