摘要:本文结合中海壳牌PG190011管线电伴热项目施工经验,对电气施工的质量控制作业技术和成套配电柜安装、接地及防雷装置安装、电缆桥架安装及电缆敷设质量控制要点进行了探讨,对电气施工遇到的主要问题进行了研究,并针对性地提出了防治措施。以便以后具有借鉴之意义。
关键词:电气施工;电柜安装;探讨
Abstract: combining with the CSPC PG190011 pipeline electric heating project construction experience, the construction quality control to the electric homework technology and complete distribution ark installation, grounding and lightning protection equipment installation, cable tray installation and cable laying quality control points, the paper discusses the construction of the main problems of the electrical meet, and puts forward specific prevention and control measures. With the meaning of the reference for later.
Keywords: electrical construction; Electric cabinet installation; explore
中圖分类号:TU976+.1文献标识码:A文章编号:
工程概况
工程名称:中海壳牌PG190011管线电伴热项目配电柜安装
变电站名称:250变电站
盘柜名:DP01
安装的位置:SB250NO2-RR2-Q
施工图号:BM-8530-1600-8011
工程工作量:变电所安装部分,低压柜安装1台,低压动力电缆敷设约1070米、控制电缆2200米。户外终端头制作安装(干包式)25个,控制电缆头制作安装34个。电缆桥架揭盖盖板300米。交流380V送配电设备系统调试1套。本工程的施工技术关键本工程关键在变电所的低压柜的安装及电缆敷设,这部分工作直接影响本工程进度。因此,这部分工作必须认真、细致安排。施工人员、质量体系和安全机构的安排具体见图1所示,具体的施工程序见图2所示。
图1组织结构图
图2 施工流程图
电气施工质量控制要点
2 .1成套配电柜安装质量控制要点
盘柜安装时,用线锤、水平尺、钢尺等工具对其质量进行跟踪检查。保证柜体水平度、垂直度、柜间间隙在允许的范围内。扩建技改项目中,常遇到在原预留孔添加柜子情况,低压配电屏母线系统分段布置于开关柜顶部的母线隔室内,设备出厂时不能整体组装,所以施工时仅采用更换或拆除绝缘支撑件来重新调整母线。母线搭接面的质量检验是质量控制的重点。以前母线接触面,允许用塞尺检查, 按(GBJ 149- 90)规定,监理应严格要求安装单位用力矩扳手紧固母线的连接螺栓,达到规定的钢制螺栓紧固力矩值,以保证母线接触紧密,减少接触电阻。
2.2 接地及防雷装置安装质量控制要点
接地极的位置与管径符合设计要求,接地线与接地极的焊接与防腐。扁钢的搭接长度应为其宽度的两倍,三面施焊,圆钢的搭接长度应为其直径的六倍,双面施焊;扁钢与角钢焊接、扁钢与钢管时,应将扁钢弯成直角形或弧形与钢管或角钢焊接,以满足搭接面要求,并应刷沥青油两道防腐,全部铁件都需镀锌。利用结构柱内主筋作防雷引下线时,自下而上需要是用作有标记两根以上主筋;屋顶避雷带的作法,避雷带采用扁钢镀锌或圆钢;平面屋顶上所有凸起的管道或金属构筑物、爬梯等,都需和避雷带连接;利用屋面金属扶手栏杆做避雷带时,拐弯处应做成圆弧的活弯,栏杆应和接地引下线可靠焊接;测试点的制作需按设计要求和施工规范规定。
2.3 电缆桥架安装及电缆敷设质量控制要点
电缆桥架安装及电缆敷设, 是供电系统的基础工作,战线长,工作量大。桥架安装重点检查现场放线,安装、立柱选用、固定应正确,焊接固定牢靠,立柱应竖直横平,其垂直偏差不允许超过规定,其间距应符合设计负载要求;立柱垂直与横撑应,其偏差不允许超过规定值,开口销安装正确,连接应牢靠,层间最小允许净距应符合规定。电缆敷设主要抓组织的工作,首先熟悉图纸要求的走向、等级、层数, 施工单位做好电缆放线计划, 画出电缆敷设次序、走向示意图, 以便敷设时大量人员有序地搬运、敷设电缆;电缆敷设占槽率: 动力电缆、控制电缆占槽率不得超过75%;电缆不得有损伤、扭绞及漏、渗油现象。敷设过程中,严格按设计文件及施工规范要求。将控制电缆和动力电缆分开敷设。垂直敷设电缆时应敷设一根绑扎一根,电缆全部敷设完后要每隔2米用尼龙绑扎带或阻燃尼龙绳绑扎一道。这一阶段质量控制主要采用旁站方式,通过监理旁站见证电气试验检测产生的每一数据和发生的现象,符合规程规范和设计要求。监督部门主要根据规程规范和设计要求监督调试步骤、程序和数据的真实性。绝缘电阻和接地电阻对接地装置的测试应按项目设计要求进行,接地电阻值符合设计要求,绝缘电阻满足规程规范和设计要求。
施工容易出现的质量问题以及采取的措施
3.1接地装置工程质量问题及防治措
接地扁钢连接时焊肉不均匀:首先调整好焊机的电流量,再施焊;焊一遍达不到要求,再焊一遍,直到符合要求为止。接地体埋深不合格:接地体敷设位置正确,连接牢固,接地体埋设深度距地面符合设计要求并不小于0 . 6m。电气装置的每个接地部分串联连接:电气装置的每个接地部分应以单独的接地线与接地干线相连接,不得在一个接地线中串接几个需要接地部分。接地装置焊接部位不作防腐处理:焊接完毕应及时防腐。接地线跨越变形缝无补偿装置:接地线应牢固、平直,固定点间距均匀,跨越变形缝有补偿装置,可用接地线本身弯成弧状代替;穿墙有保护管,油漆防腐平整。
3.2盘(柜)安装工程质量问题及防治措施
型钢基础框架几何尺寸和盘箱柜不相符,用气焊扩孔平直度达不到规定要求:制作盘箱型钢基础框架前,首先将所使用的型钢平直,将“死弯” 的部位切割掉,用机器开孔。固定支架、垫板安装后露出地平面,影响外观质量,甚至影响手车进出柜操作:固定框架用的支架、垫铁在使用前,应先将土建地面标高确定好,再确定安放位置,但必须放置在地平面以下。接地安装不规范:盘柜接地应从接地干线直接接至基础框架螺丝和箱的接地母排上,不应该从接地干线引自基础框架后再接到箱内母排上。配电柜安装不规范:配电柜两侧及顶部的隔板应齐全、安装牢固、无损坏;柜内所有设备应安装牢固;螺栓、销子、螺帽、垫圈都应齐全;回路名称和零件标号齐全,柜内清洁。手车推拉灵活和轻便不够:协助供货商处理。配电柜试验前,未检查螺栓:配电柜安装完毕后,在交接试验前应将柜内所有电器螺栓的松紧程度检查一遍,有脱漆时,应喷刷补齐。
3.3导管敷设工程质量问题及防治措施
隐蔽导管敷设在电气工程中占到非常大的比例,很容易出现质量问题的技术环节,它是电气工程施工的一个基本环节,很多施工人员很容易产生麻痹心理,应该引起我们的足够重视。导管敷设施工中,在穿线作业时极容易划开导线的绝缘层,造成重大安全隐患。金属材质导管的常见问题是管口不做处理,裁剪下来的管口有许多毛刺,这些金属毛刺锋利异常, 安装完毕后,在使用运行中,一旦发生问题,轻者造成短路停电,且难以维修,重者造成火灾,带来不可挽回的重大损失。为了防止这类质量问题的发生,本文认为首先应严格操作规程,对金属导管管口剪裁完成后,按相关规程要求,管口形状应当进行处理,必须做成喇叭形或加保护套。施工过程中,要加强技术指导和监督检查,发现管口不符合技术要求的,要坚决不准进行穿线施工作业。关于FPC阻燃管的施工,质量问题集中出现在穿过现浇板或柱子时或接头处,阻燃管因材质的原因,加上壁薄的物理特性,对温度的变化敏感,因此在穿过现浇梁或柱子时极易被压扁或混凝土振捣时被损伤破裂,灌进沙浆,穿线时无法通过。接头处容易出现的问题, 主要是因为没有达到要求粘接强度时,被压弯拉长,从接头套管中脱出,解决这些问题的办法:在FPC管穿过现浇梁柱时加上套管,避免因混凝土振捣时被损伤破裂或被压扁,造成无法接线的难题。关于接头问题的处理,一般是在接头时提前粘接,达到要求强度之后再上墙,可以避免问题的发生。
结论
确保电气施工质量对于整个项目质量非常重要,本文结合中海壳牌PG190011管线电伴热项目施工经验,对电气施工质量遇到的主要问题进行深入的探讨和研究,并针对性地提出了防治措施。以便以后具有借鉴之意义。
参考文献:
[1] 薛国清.智能建筑的电气保护与接地[J].山西建筑,2005,31(06) :133-134..
[2] 陆有娟.建筑物施工中的电气施工综述[J].山西建筑,2007,33(27):202-203.
关键词:电气施工;电柜安装;探讨
Abstract: combining with the CSPC PG190011 pipeline electric heating project construction experience, the construction quality control to the electric homework technology and complete distribution ark installation, grounding and lightning protection equipment installation, cable tray installation and cable laying quality control points, the paper discusses the construction of the main problems of the electrical meet, and puts forward specific prevention and control measures. With the meaning of the reference for later.
Keywords: electrical construction; Electric cabinet installation; explore
中圖分类号:TU976+.1文献标识码:A文章编号:
工程概况
工程名称:中海壳牌PG190011管线电伴热项目配电柜安装
变电站名称:250变电站
盘柜名:DP01
安装的位置:SB250NO2-RR2-Q
施工图号:BM-8530-1600-8011
工程工作量:变电所安装部分,低压柜安装1台,低压动力电缆敷设约1070米、控制电缆2200米。户外终端头制作安装(干包式)25个,控制电缆头制作安装34个。电缆桥架揭盖盖板300米。交流380V送配电设备系统调试1套。本工程的施工技术关键本工程关键在变电所的低压柜的安装及电缆敷设,这部分工作直接影响本工程进度。因此,这部分工作必须认真、细致安排。施工人员、质量体系和安全机构的安排具体见图1所示,具体的施工程序见图2所示。
图1组织结构图
图2 施工流程图
电气施工质量控制要点
2 .1成套配电柜安装质量控制要点
盘柜安装时,用线锤、水平尺、钢尺等工具对其质量进行跟踪检查。保证柜体水平度、垂直度、柜间间隙在允许的范围内。扩建技改项目中,常遇到在原预留孔添加柜子情况,低压配电屏母线系统分段布置于开关柜顶部的母线隔室内,设备出厂时不能整体组装,所以施工时仅采用更换或拆除绝缘支撑件来重新调整母线。母线搭接面的质量检验是质量控制的重点。以前母线接触面,允许用塞尺检查, 按(GBJ 149- 90)规定,监理应严格要求安装单位用力矩扳手紧固母线的连接螺栓,达到规定的钢制螺栓紧固力矩值,以保证母线接触紧密,减少接触电阻。
2.2 接地及防雷装置安装质量控制要点
接地极的位置与管径符合设计要求,接地线与接地极的焊接与防腐。扁钢的搭接长度应为其宽度的两倍,三面施焊,圆钢的搭接长度应为其直径的六倍,双面施焊;扁钢与角钢焊接、扁钢与钢管时,应将扁钢弯成直角形或弧形与钢管或角钢焊接,以满足搭接面要求,并应刷沥青油两道防腐,全部铁件都需镀锌。利用结构柱内主筋作防雷引下线时,自下而上需要是用作有标记两根以上主筋;屋顶避雷带的作法,避雷带采用扁钢镀锌或圆钢;平面屋顶上所有凸起的管道或金属构筑物、爬梯等,都需和避雷带连接;利用屋面金属扶手栏杆做避雷带时,拐弯处应做成圆弧的活弯,栏杆应和接地引下线可靠焊接;测试点的制作需按设计要求和施工规范规定。
2.3 电缆桥架安装及电缆敷设质量控制要点
电缆桥架安装及电缆敷设, 是供电系统的基础工作,战线长,工作量大。桥架安装重点检查现场放线,安装、立柱选用、固定应正确,焊接固定牢靠,立柱应竖直横平,其垂直偏差不允许超过规定,其间距应符合设计负载要求;立柱垂直与横撑应,其偏差不允许超过规定值,开口销安装正确,连接应牢靠,层间最小允许净距应符合规定。电缆敷设主要抓组织的工作,首先熟悉图纸要求的走向、等级、层数, 施工单位做好电缆放线计划, 画出电缆敷设次序、走向示意图, 以便敷设时大量人员有序地搬运、敷设电缆;电缆敷设占槽率: 动力电缆、控制电缆占槽率不得超过75%;电缆不得有损伤、扭绞及漏、渗油现象。敷设过程中,严格按设计文件及施工规范要求。将控制电缆和动力电缆分开敷设。垂直敷设电缆时应敷设一根绑扎一根,电缆全部敷设完后要每隔2米用尼龙绑扎带或阻燃尼龙绳绑扎一道。这一阶段质量控制主要采用旁站方式,通过监理旁站见证电气试验检测产生的每一数据和发生的现象,符合规程规范和设计要求。监督部门主要根据规程规范和设计要求监督调试步骤、程序和数据的真实性。绝缘电阻和接地电阻对接地装置的测试应按项目设计要求进行,接地电阻值符合设计要求,绝缘电阻满足规程规范和设计要求。
施工容易出现的质量问题以及采取的措施
3.1接地装置工程质量问题及防治措
接地扁钢连接时焊肉不均匀:首先调整好焊机的电流量,再施焊;焊一遍达不到要求,再焊一遍,直到符合要求为止。接地体埋深不合格:接地体敷设位置正确,连接牢固,接地体埋设深度距地面符合设计要求并不小于0 . 6m。电气装置的每个接地部分串联连接:电气装置的每个接地部分应以单独的接地线与接地干线相连接,不得在一个接地线中串接几个需要接地部分。接地装置焊接部位不作防腐处理:焊接完毕应及时防腐。接地线跨越变形缝无补偿装置:接地线应牢固、平直,固定点间距均匀,跨越变形缝有补偿装置,可用接地线本身弯成弧状代替;穿墙有保护管,油漆防腐平整。
3.2盘(柜)安装工程质量问题及防治措施
型钢基础框架几何尺寸和盘箱柜不相符,用气焊扩孔平直度达不到规定要求:制作盘箱型钢基础框架前,首先将所使用的型钢平直,将“死弯” 的部位切割掉,用机器开孔。固定支架、垫板安装后露出地平面,影响外观质量,甚至影响手车进出柜操作:固定框架用的支架、垫铁在使用前,应先将土建地面标高确定好,再确定安放位置,但必须放置在地平面以下。接地安装不规范:盘柜接地应从接地干线直接接至基础框架螺丝和箱的接地母排上,不应该从接地干线引自基础框架后再接到箱内母排上。配电柜安装不规范:配电柜两侧及顶部的隔板应齐全、安装牢固、无损坏;柜内所有设备应安装牢固;螺栓、销子、螺帽、垫圈都应齐全;回路名称和零件标号齐全,柜内清洁。手车推拉灵活和轻便不够:协助供货商处理。配电柜试验前,未检查螺栓:配电柜安装完毕后,在交接试验前应将柜内所有电器螺栓的松紧程度检查一遍,有脱漆时,应喷刷补齐。
3.3导管敷设工程质量问题及防治措施
隐蔽导管敷设在电气工程中占到非常大的比例,很容易出现质量问题的技术环节,它是电气工程施工的一个基本环节,很多施工人员很容易产生麻痹心理,应该引起我们的足够重视。导管敷设施工中,在穿线作业时极容易划开导线的绝缘层,造成重大安全隐患。金属材质导管的常见问题是管口不做处理,裁剪下来的管口有许多毛刺,这些金属毛刺锋利异常, 安装完毕后,在使用运行中,一旦发生问题,轻者造成短路停电,且难以维修,重者造成火灾,带来不可挽回的重大损失。为了防止这类质量问题的发生,本文认为首先应严格操作规程,对金属导管管口剪裁完成后,按相关规程要求,管口形状应当进行处理,必须做成喇叭形或加保护套。施工过程中,要加强技术指导和监督检查,发现管口不符合技术要求的,要坚决不准进行穿线施工作业。关于FPC阻燃管的施工,质量问题集中出现在穿过现浇板或柱子时或接头处,阻燃管因材质的原因,加上壁薄的物理特性,对温度的变化敏感,因此在穿过现浇梁或柱子时极易被压扁或混凝土振捣时被损伤破裂,灌进沙浆,穿线时无法通过。接头处容易出现的问题, 主要是因为没有达到要求粘接强度时,被压弯拉长,从接头套管中脱出,解决这些问题的办法:在FPC管穿过现浇梁柱时加上套管,避免因混凝土振捣时被损伤破裂或被压扁,造成无法接线的难题。关于接头问题的处理,一般是在接头时提前粘接,达到要求强度之后再上墙,可以避免问题的发生。
结论
确保电气施工质量对于整个项目质量非常重要,本文结合中海壳牌PG190011管线电伴热项目施工经验,对电气施工质量遇到的主要问题进行深入的探讨和研究,并针对性地提出了防治措施。以便以后具有借鉴之意义。