论文部分内容阅读
1.路基汽车运输土石方增运定额LY-127,LY-130,其定额单位为1Km,当实际运距不足1Km,如300m,定额应如何正确使用?采用定额乘0.3是否可以? 答:路基自卸汽车运输土石方增运定额是综合编制的,当运距不足1Km时,按1Km计。例如2.3km按3km计,4.8km按5km计,不能采取乘0.3或乘0.8的办法使用增运定额。 2.路基沙漠防护定额中LY-398树条沙障,该定额能否具体介绍一下,如树条高度、有无固定桩等等,具体是多少?
1. Subgrade car transport earthworking fixed quotas LY-127, LY-130, the quota unit is 1Km, when the actual distance less than 1Km, such as 300m, how to use the quota correctly? Unloading car transport Earthworking quota is a comprehensive preparation, when the distance less than 1Km, according to 1Km meter. For example 2.3km by 3km meter, 4.8km by 5km meter, can not take the 0.3 or 0.8 by the use of transport quotas. 2. Subgrade Desert Protection quota LY-398 tree sand barrier, the quota can be specific about, such as tree height, with or without fixed pile, etc., specifically how much?