论文部分内容阅读
第三讲 监理工程师的工作制度和对工程施工进度的监理方法一、监理工程师的工作制度水利水电工程建设集资源,人力、设备、时间、管理、技术于一体,生产力诸要素高度集中。建设过程中由于规模、地点、方式以及参加建设单位等异同而成为一种一次性单件生产过程。各种生产力要素的投入往往在不同阶段、不同空间而时断时续、时紧时松,存在多种影响因素和风险因素。然而,肩负对工程建设监督和管理职责的监理工
Lecture 3 Supervising Engineer’s Work System and Supervision Method for Construction Progress I. System of Supervising Engineer’s Work The construction of water conservancy and hydropower project integrates resources, manpower, equipment, time, management and technology, and all the elements of productivity are highly concentrated. Due to the similarities and differences in scale, location, mode and participation in the construction unit, the construction process has become a one-time one-piece production process. Various factors of productive forces are often invested in different stages, intermittent and intermittent in different space, when the time is tight and loose, there are many influencing factors and risk factors. However, supervisors who are responsible for supervising and managing construction work are supervised