1978年底至1979年初,我们采用蒸汽热模养护方法完成了北京市第一机床厂大模板住宅楼8个楼层的墙体混凝土。完成结构工程建筑面积9600平方米,现浇混凝土实物量1664立方米。这是我们在冬季进行大模板工程结构施工的一次有益实践。
From the end of 1978 to the beginning of 1979, we completed the construction of the wall concrete of the 8 floors of the large formwork residential building of the No. 1 Machine Tool Plant in Beijing using the steam hot mold maintenance method. The completion of structural engineering construction area of 9600 square meters, in-situ concrete volume of 1664 cubic meters. This is a useful practice for us to carry out the construction of the large formwork works in winter.