【摘 要】徐楼铁矿采用井下帷幕注浆法防治岩溶裂隙水。经过两年时间,已经初见成效。在实施防治水工程过程中,并非理想化,而是根据生产需要适时调整,取得了一些宝贵经验,这些经验对今后防治水有重要指导作用,对类似矿山也有借鉴意义。
【关键词】岩溶裂隙水;井下帷幕注浆;经验
Sket chup the flood prevention work smin the iron
Lan Zhong-ping
(Haibei Xulou Minging Company Ltd, Haibei Anhui 235000)
【Abstract】Underground Grout curtain is used for control of the Karst ground water in XULOU iron ore. after two years have begun to deliver results. in implementing the water project, not to idealize, but according to the need for timely and made some valuable experience, the experience in the prevention and control of water is important for guiding role, similar to mine. there are also using.
【Key words】Karst ground water;Underground Grout curtain;Experience.
1. 矿井概况
徐楼铁矿为一接触交代型矽卡岩磁铁矿床,是一座水文地质条件极其复杂的大水地下矿山。矿井全区包括石楼、双庄、史小楼三个矿床,目前开采石楼矿床一矿带。矿山采用竖井侧翼式开拓,上向水平分层胶结充填法和嗣后充填房柱法开采矿体的联合开采方法。
2. 地质水文状况
石楼矿床矿体埋深48~385m,厚20-35米,埋深48~56m,走向长500m,呈透镜体,产状平缓。矿体上盘及四周围岩均为厚度大的中奥陶系灰岩、大理岩强含水层,风化严重,岩溶裂隙发育,裂隙交错成网状,富水性较强。矿体下盘为闪长岩,为隔水层。见图1[1]。
矿区地质老钻孔封孔质量差,第四系砂层中孔隙水及大理岩含水层裂隙岩溶承压水可通过那些未封好的钻孔直接灌入井下工作面。另外大理岩含水层在矿区北部地段因隔水层缺失出现天窗与第四系砂层相通,使矿井补给水更丰富,地下水动储量大,增大了矿山开采的难度[2]。
图1 石楼矿床Ⅰ矿带A3线剖面图
3. 帷幕注浆取得的成效
该矿采用井下帷幕注浆法防治水,目前已取得显著效果,大岩溶裂隙已被封堵,大水已被基本治理。防治水工程通过检查孔及锚索孔检验合格,开采采场无灾害性水患。
帷幕注浆前在石楼矿床一矿带0、1、2采区施工超前探水钻孔和帷幕注浆孔327个,各孔深35-60米,钻孔涌水量一般为50~100m3/h,少部分钻孔涌水量达200~300m3/h,部分钻孔涌水量小于50m3/h,个别钻孔见漏水或渗水,很少见到没有水的钻孔。帷幕注浆后在0、1、2采区施工了检查孔(垂直探矿孔及长锚索孔)。大部分无水,少部分滴水或出水0.2~2m3/h。
实施帷幕注浆工程之前,井下到处出现涌水、漏水或渗水现象,而现在井下基本见不到渗水现象,同时,从井下揭露巷道可看到,大部分的导水裂隙中都可见到水泥结石,断层两盘被水泥胶结,部分检查孔也取到了水泥结石。
对导通地面的封孔不良老钻孔,已基本被封堵。工作面揭露A63、A52、A55、A58孔已无水,孔内见水泥结石。甚至2采区A55孔水泥浆渗出地面,凝固后成了混凝土。在掘进巷道中,探导水老钻孔水5次,都未见水。说明注浆封死了老钻孔。
从以上几方面充分说明该区段的帷幕注浆已达到了设计要求,可以安全采矿。
4. 经验及实践体会
在实施帷幕注浆过程中,由于生产需要有时冒进,防治水工程不可能按理想化实施,但在实践中务必吸取以下经验教训。
4.1 在新区石灰岩内掘进巷道,超前探水钻孔不能布置1个,必须保证4个,便于在巷道周围岩体内通过注浆形成帷幕,保证施工安全。2007年12月在-58水平回风巷内施工一个钻孔,虽注了600多吨水泥,但后期掘巷道时出水200m3/h淹井。
4.2 在石灰岩内掘进巷道,先期深孔探水必须做好,否则后患无穷。如-58水平回风巷近东大巷天井拐弯处,因以前为了抢进度未注浆,虽然水小,但后期深孔探水和帷幕注浆时与该处导通,注浆压力上不去。
4.3 在帷幕注浆前期,可考虑在不同位置打孔,后采用群孔注浆,特别是矿体边缘外围孔,效果较好,可以控制浆液流向,保证在矿体周围结实。帷幕注浆后期,由于要抢生产,可以不进行群孔注浆,因为这时大岩溶裂隙已被封堵,水力联系较差,可以打一孔注一孔。
4.4 注意埋孔口管后应试压,防止注浆达高压时孔口管脱落。注意观察施工过程中洞室岩壁是否破碎渗水,如渗水,可以钻进一点后注浆,最后钻完再注浆,这样可以起到加固洞室岩体作用。
4.5 遇到注浆不起压的水文孔,可以在保证一定注浆量前提下(如定为500吨水泥)封孔,后打检查孔检验,如有水注浆,最后再打第二次检查孔检验。或在其它地方打孔,采用群孔注浆,看是否串孔。
4.6 注浆终压的确定,既要考虑岩体抗张强度,又要考虑岩体分布位置。如注浆孔周围是泥灰岩,注浆终压不应超过4MPa;如为褐铁矿,注浆终压不应超过5~6MPa;如为石灰岩或大理岩,注浆终压可达6MPa以上(5~12倍水压)。具体情况视岩体裂隙发育率而定,裂隙愈发育,取小值,裂隙不发育,取大值。对-45水平以上岩体(顶部岩柱,为风化带,上层是砂层、含碎石粘土)注浆,终压可达5~6MPa,尽管上部岩体在注浆压力下有被破坏现象,但与水泥结合后会形成帷幕复合体后仍起到了隔水效果。
4.7 浆液浓度应根据裂隙宽度而定,对石灰岩或泥灰岩,因裂隙较宽,浓度一般定位1:1(水灰比),对矿体(磁铁矿或褐铁矿),裂隙细小,浓度一般定位2:1(水灰比)。打水文孔时尽量穿过矿体进入灰岩内,便于大量注浆。
4.8 在一个硐室施工帷幕孔,不能全部打完了才注浆。必须先施工一半注一半,后期检查前期注浆效果。
4.9 帷幕注浆不能全部堵死顶板及周围岩溶裂隙水。从1采区来看,该区前期帷幕孔也打了,后期加密孔也打了,但是顶板还是有水。主要是灰岩内有黄泥,影响浆液扩散。因此对中深孔采场,顶部必须打长锚索支护,利用打长锚索孔时最后一次注浆封堵。
4.10 顶板水没有治好,不能在下面施工天井和下面20米处施工凿岩巷。如3、4、5采区,否则注浆时巷道内跑浆影响注浆效果。
4.11 矿体与下盘闪长岩接触带有裂隙水,虽然水不大,应引起重视。我矿0采区0采场、1采区1-2采场(-100水平以下)由于底板水未处理,开采时出水不得不停止。
4.12 老钻孔应引起重视。虽经过帷幕注浆,大部分老钻孔被封死了,但也有部分钻孔没有封死,如A58孔,在施工出矿进路时出水。
4.13 中深孔采场因为放炮对顶板震动大,必须打长锚索护顶,同时也是对帷幕注浆进行一次检验,一次补救,有水注浆,无水封孔。采场采后充填接顶一定要密实,防止顶板冒落出水,不密实应注浆。
参考文献
[1] 安徽省濉溪县徐楼铁矿地质勘察报告[R]2867.安徽省地质局325队.1971.12 :39.
[2] 辛小毛、曾先贵、王 亮等.徐楼铁矿井下近矿体帷幕注浆实施方案[R].长沙矿山研究院.2008.12:9.
[文章编号]1006-7619(2010)06-12-537
[作者简介] 兰中平(1969-),男,汉族,,四川岳池县人,本科,工程师,93年毕业于湘潭矿业学院地质系,在安徽省淮北徐楼矿业有限公司从事矿山水文地质和工程地质研究,并担任矿井防治水工程负责人。
【关键词】岩溶裂隙水;井下帷幕注浆;经验
Sket chup the flood prevention work smin the iron
Lan Zhong-ping
(Haibei Xulou Minging Company Ltd, Haibei Anhui 235000)
【Abstract】Underground Grout curtain is used for control of the Karst ground water in XULOU iron ore. after two years have begun to deliver results. in implementing the water project, not to idealize, but according to the need for timely and made some valuable experience, the experience in the prevention and control of water is important for guiding role, similar to mine. there are also using.
【Key words】Karst ground water;Underground Grout curtain;Experience.
1. 矿井概况
徐楼铁矿为一接触交代型矽卡岩磁铁矿床,是一座水文地质条件极其复杂的大水地下矿山。矿井全区包括石楼、双庄、史小楼三个矿床,目前开采石楼矿床一矿带。矿山采用竖井侧翼式开拓,上向水平分层胶结充填法和嗣后充填房柱法开采矿体的联合开采方法。
2. 地质水文状况
石楼矿床矿体埋深48~385m,厚20-35米,埋深48~56m,走向长500m,呈透镜体,产状平缓。矿体上盘及四周围岩均为厚度大的中奥陶系灰岩、大理岩强含水层,风化严重,岩溶裂隙发育,裂隙交错成网状,富水性较强。矿体下盘为闪长岩,为隔水层。见图1[1]。
矿区地质老钻孔封孔质量差,第四系砂层中孔隙水及大理岩含水层裂隙岩溶承压水可通过那些未封好的钻孔直接灌入井下工作面。另外大理岩含水层在矿区北部地段因隔水层缺失出现天窗与第四系砂层相通,使矿井补给水更丰富,地下水动储量大,增大了矿山开采的难度[2]。
图1 石楼矿床Ⅰ矿带A3线剖面图
3. 帷幕注浆取得的成效
该矿采用井下帷幕注浆法防治水,目前已取得显著效果,大岩溶裂隙已被封堵,大水已被基本治理。防治水工程通过检查孔及锚索孔检验合格,开采采场无灾害性水患。
帷幕注浆前在石楼矿床一矿带0、1、2采区施工超前探水钻孔和帷幕注浆孔327个,各孔深35-60米,钻孔涌水量一般为50~100m3/h,少部分钻孔涌水量达200~300m3/h,部分钻孔涌水量小于50m3/h,个别钻孔见漏水或渗水,很少见到没有水的钻孔。帷幕注浆后在0、1、2采区施工了检查孔(垂直探矿孔及长锚索孔)。大部分无水,少部分滴水或出水0.2~2m3/h。
实施帷幕注浆工程之前,井下到处出现涌水、漏水或渗水现象,而现在井下基本见不到渗水现象,同时,从井下揭露巷道可看到,大部分的导水裂隙中都可见到水泥结石,断层两盘被水泥胶结,部分检查孔也取到了水泥结石。
对导通地面的封孔不良老钻孔,已基本被封堵。工作面揭露A63、A52、A55、A58孔已无水,孔内见水泥结石。甚至2采区A55孔水泥浆渗出地面,凝固后成了混凝土。在掘进巷道中,探导水老钻孔水5次,都未见水。说明注浆封死了老钻孔。
从以上几方面充分说明该区段的帷幕注浆已达到了设计要求,可以安全采矿。
4. 经验及实践体会
在实施帷幕注浆过程中,由于生产需要有时冒进,防治水工程不可能按理想化实施,但在实践中务必吸取以下经验教训。
4.1 在新区石灰岩内掘进巷道,超前探水钻孔不能布置1个,必须保证4个,便于在巷道周围岩体内通过注浆形成帷幕,保证施工安全。2007年12月在-58水平回风巷内施工一个钻孔,虽注了600多吨水泥,但后期掘巷道时出水200m3/h淹井。
4.2 在石灰岩内掘进巷道,先期深孔探水必须做好,否则后患无穷。如-58水平回风巷近东大巷天井拐弯处,因以前为了抢进度未注浆,虽然水小,但后期深孔探水和帷幕注浆时与该处导通,注浆压力上不去。
4.3 在帷幕注浆前期,可考虑在不同位置打孔,后采用群孔注浆,特别是矿体边缘外围孔,效果较好,可以控制浆液流向,保证在矿体周围结实。帷幕注浆后期,由于要抢生产,可以不进行群孔注浆,因为这时大岩溶裂隙已被封堵,水力联系较差,可以打一孔注一孔。
4.4 注意埋孔口管后应试压,防止注浆达高压时孔口管脱落。注意观察施工过程中洞室岩壁是否破碎渗水,如渗水,可以钻进一点后注浆,最后钻完再注浆,这样可以起到加固洞室岩体作用。
4.5 遇到注浆不起压的水文孔,可以在保证一定注浆量前提下(如定为500吨水泥)封孔,后打检查孔检验,如有水注浆,最后再打第二次检查孔检验。或在其它地方打孔,采用群孔注浆,看是否串孔。
4.6 注浆终压的确定,既要考虑岩体抗张强度,又要考虑岩体分布位置。如注浆孔周围是泥灰岩,注浆终压不应超过4MPa;如为褐铁矿,注浆终压不应超过5~6MPa;如为石灰岩或大理岩,注浆终压可达6MPa以上(5~12倍水压)。具体情况视岩体裂隙发育率而定,裂隙愈发育,取小值,裂隙不发育,取大值。对-45水平以上岩体(顶部岩柱,为风化带,上层是砂层、含碎石粘土)注浆,终压可达5~6MPa,尽管上部岩体在注浆压力下有被破坏现象,但与水泥结合后会形成帷幕复合体后仍起到了隔水效果。
4.7 浆液浓度应根据裂隙宽度而定,对石灰岩或泥灰岩,因裂隙较宽,浓度一般定位1:1(水灰比),对矿体(磁铁矿或褐铁矿),裂隙细小,浓度一般定位2:1(水灰比)。打水文孔时尽量穿过矿体进入灰岩内,便于大量注浆。
4.8 在一个硐室施工帷幕孔,不能全部打完了才注浆。必须先施工一半注一半,后期检查前期注浆效果。
4.9 帷幕注浆不能全部堵死顶板及周围岩溶裂隙水。从1采区来看,该区前期帷幕孔也打了,后期加密孔也打了,但是顶板还是有水。主要是灰岩内有黄泥,影响浆液扩散。因此对中深孔采场,顶部必须打长锚索支护,利用打长锚索孔时最后一次注浆封堵。
4.10 顶板水没有治好,不能在下面施工天井和下面20米处施工凿岩巷。如3、4、5采区,否则注浆时巷道内跑浆影响注浆效果。
4.11 矿体与下盘闪长岩接触带有裂隙水,虽然水不大,应引起重视。我矿0采区0采场、1采区1-2采场(-100水平以下)由于底板水未处理,开采时出水不得不停止。
4.12 老钻孔应引起重视。虽经过帷幕注浆,大部分老钻孔被封死了,但也有部分钻孔没有封死,如A58孔,在施工出矿进路时出水。
4.13 中深孔采场因为放炮对顶板震动大,必须打长锚索护顶,同时也是对帷幕注浆进行一次检验,一次补救,有水注浆,无水封孔。采场采后充填接顶一定要密实,防止顶板冒落出水,不密实应注浆。
参考文献
[1] 安徽省濉溪县徐楼铁矿地质勘察报告[R]2867.安徽省地质局325队.1971.12 :39.
[2] 辛小毛、曾先贵、王 亮等.徐楼铁矿井下近矿体帷幕注浆实施方案[R].长沙矿山研究院.2008.12:9.
[文章编号]1006-7619(2010)06-12-537
[作者简介] 兰中平(1969-),男,汉族,,四川岳池县人,本科,工程师,93年毕业于湘潭矿业学院地质系,在安徽省淮北徐楼矿业有限公司从事矿山水文地质和工程地质研究,并担任矿井防治水工程负责人。