今年以来,炼钢厂在生产组织是面临二期连铸紧锣密鼓地施工,一号转炉而临改造性大修,外部条件不够完善等问题,给正常生产带来一定难度。 9月21日二期连铸热负荷试车成功之后,由于原料如铁水、氧气等不足,给生产组织带来困难。在生产中将一号铸机的定期检修与二号铸机的止常拉坯有机地结合在一起,合理调配钢水罐,使二期连铸自热负荷试车以来,成功实现五连浇,七连浇。1~9月该厂共
Since the beginning of this year, the steel mills face the problems of two phases of continuous casting, one-stage converter overhaul and overhaul, and inadequate external conditions in the production organization. This poses certain difficulties for normal production. On September 21, after the successful trial run of the second-stage continuous casting heat load, due to the shortage of raw materials such as hot metal and oxygen, it brings difficulties to the production organization. In production, the regular maintenance of No.1 casting machine is combined organically with the normal casting of No.2 casting machine to rationally allocate the steel water tank so that the continuous casting of self-heating load in the second-stage continuous casting process has succeeded in realizing five continuous casting, seven Even pouring. 1 ~ September the plant a total of