燕山石化公司30万吨乙烯改造工程是国家“八·五”重点技改项目,从1992年6月批准可行性研究报告,到1994年9月建成投产,仅用了27个月零18天,工程投资不仅没有突破28亿元的概算,而且还节约了5000多万元,创造了建设速度、工程质量、投资控制、施工组织的新水平。乙烯装置改造后,使燕化的乙烯生产能力增加了15万吨,公司的各项经济
Yanshan Petrochemical Company’s 300,000-ton ethylene renovation project is a national “Eighth Five-Year Plan” key technological transformation project. It approved the feasibility study report in June 1992 and completed and put into operation in September 1994. It took only 27 months and 18 days. The project investment has not only failed to break through the 2.8 billion yuan estimate, but also saved more than 50 million yuan, creating a new level of construction speed, project quality, investment control, and construction organization. After the transformation of the ethylene plant, Yanhua’s ethylene production capacity increased by 150,000 tons, the company’s various economic