内蒙古包头市新兴盛能源有限公司二期50万方/天LNG项目是杭州福斯达实业集团公司负责工艺包设计、全厂工艺设备、工艺非标设备的设计与制造、控制系统、电气系统等设备的采购、项目管理、调试、培训等技术支持等服务项目,历经一年的建设,于2015年4月25日顺利调试出液达产。50万方/天LNG项目于2014年3月份开始设备供货、安装,项目于2014年10月完成所有动、静设备及管道连接
Inner Mongolia Baotou Xinxing Sheng Energy Co., Ltd. Phase II 500,000 square / day LNG project is Hangzhou Fosida Industrial Group Co., Ltd. is responsible for package design, the whole plant process equipment, non-standard equipment design and manufacturing processes, control systems, electrical systems Equipment procurement, project management, commissioning, training and other technical services and other services, after a year of construction, in April 25, 2015 successfully debugging a solution of liquid production. 50kph / day LNG project began to supply and install equipment in March 2014. The project completed all moving and static equipment and pipeline connections in October 2014