论文部分内容阅读
案例2000年10月,杨某在开发商尚未取得某楼盘商品房预售许可证的情况下,和开发商签订了该楼盘某商品房的非正式购房合同。约定开发商应当最迟于2001年9月1日交付房屋,逾期交房将按每天房价的万分之五支付违约金。逾期交房超过一个月,杨某有权解除合同,开发商需退还已付房款并双倍返还定金。同年12月,开发商拿到了预售许
Case In October 2000, Yang Mou developers have not yet obtained a real estate pre-sale permit case, and developers signed a real estate purchase of real estate contract for the informal. Contracted developers should be the delivery of housing by September 1, 2001 at the latest, overdue delivery will be paid at 10% of the daily price of liquidated damages. Overdue delivery more than a month, Yang have the right to rescind the contract, developers need to refund the paid back and double the deposit. In December the same year, the developer got pre-sale permit