1996年,东曲矿选煤厂把职工收入与单位效益挂钩,职工奋力拚搏,生产精煤80.35万t,完成年初计划的178.5%;精煤回收率达45.26%,超计划5.26%:吨精煤成本比计划降低17.84元,总成本节约1433.44万元,
In 1996, the Dongqu Coal Preparation Plant linked the income of employees with the unit efficiency. The workers worked hard to produce 803,500 tons of refined coal and completed 178.5% of the plan at the beginning of the year. The recovery rate of refined coal reached 45.26%, exceeding the plan by 5.26% Coal costs lower than planned 17.84 yuan, the total cost savings of 14.3344 million yuan,