1982年3月,顿涅茨矿井掘进托拉斯第三掘进工程处,在顿涅茨М.И.加里宁矿掘进了202米的东风井井筒。该竖井是采用标准装备系统,用普通混合作业法掘进的。根据顿涅茨采矿设计院设计的采矿工程发展规划,新井布置在距М.И.加里宁矿中央采区东北6公里处。该井深800米,净直径6米,掘进直径7米,整体浇注混凝土井壁厚度为500毫米。井筒装备施工图是顿涅茨矿井施工组织
In March 1982, the Donets Mine excavated the Trust’s third heading UNDAC, which bore a 202-m east wind shaft at the Garment Mine in Donetsc. The shaft is equipped with standard equipment and is drilled with normal mixing operations. According to the design plan of the mining engineering of the Donets Mining Design Institute, the new well is arranged 6 km northeast of the central mining area of the М.И. Kalinin Mine. The depth of 800 meters, the net diameter of 6 meters, 7 meters diameter excavation, the overall wall thickness of concrete pouring 500 mm. Wellbore equipment construction drawing is Donets Mine Construction Organization