金渠金矿位于河南省灵宝县境内,矿区地处小秦岭大湖峪深部,为三门峡市属国营企业。该矿自1987年开始筹建,1989年批准长春黄金设计院的初步设计,设计生产规模采选200t/d,年产黄金×××kg,建设周期2年。 金渠金矿从1990年6月全面开工建设以来,坚持基建程序,狠抓施工管理,按照“矿山先行,采选同步,附属配套”的原则,突出重点,精心组织,采取了加强计划管理,强化调度指挥,追踪管理质量,坚持一支笔批钱,实行目标责任制等措施,仅用一年半时间,就优质高速地完成全部工程。比预定计划提前半年建成。两坑口分别于1991年5月15日和9月5日形成100t/d的出矿能力,选矿厂于1991年5月4日进行无负荷联动试车,同年7
Located in Lingbao County, Henan Province, the gold mine is located in the deep Dahuyu of the Qinling Mountains and is a state-owned enterprise of Sanmenxia City. The mine started construction in 1987 and approved the preliminary design of the Changchun Gold Design Institute in 1989. The design and production scale was adopted for mining and selection of 200t / d, with an annual output of gold ××× kg and a construction period of 2 years. Since its commencement of construction in June 1990, Jinqu Gold Mine has adhered to the capital construction program and paid close attention to construction management. In accordance with the principle of “advanced mining, synchronization of mining and mining, and ancillary facilities,” Jinqu Gold Mine highlighted the key points and carefully organized and adopted measures to strengthen planning management, Strengthen the scheduling command, tracking management quality, insist on a pen grant money, the implementation of the target responsibility system and other measures, only a year and a half, to complete the project of high quality and speed. Build six months ahead of schedule. Liangkankou, respectively, on May 15, 1991 and September 5, the formation of 100t / d of the ore out of capacity, beneficiation plant on May 4, 1991 no-load linkage test run the same year 7