我们桂林工务段管内,现有的隧道均为碎石道床。为了减少运营隧道的养护维修,改善劳动条件,适应我国国民经济建设和铁路运输日益发展的需要,根据我局“四五”规划把全局隧道改建成整体道床的要求,经段党委研究决定,组织了部分人力,选择湘桂线波寨2号隧道作为试点,采用不封锁线路的方法,修建隧道整体道床,拟取得经验后,为今后推广打下基础。波寨2号隧道全长60米,全部为直线,平坡,地质强度f=3,地层是风化泥灰岩,原线路为木枕,碎石道床,每米43公斤钢轨,行驶
Our Guilin PM section, the existing tunnels are gravel roadbed. In order to reduce the maintenance and repair of operating tunnels, improve working conditions, meet the needs of the national economic construction and the increasing development of railway transportation in our country, according to the “4 th Five-Year Plan” of our bureau, the requirements of converting the global tunnel into an integral ballast bed, Part of the manpower, select Xianggui line Porezhao No. 2 tunnel as a pilot, the method does not block lines, the construction of the tunnel as a whole bed, intended to gain experience, lay the foundation for future promotion. Bozhai 2 tunnel is 60 meters in length, all straight, flat slope, geological strength f = 3, the formation is weathered marl, the original line for the wood pillow, gravel road bed, 43 kilograms per meter rail, driving