本文拟通过对铁坑铁矿固定资产投资分析,总结经验教训,探索改造扩建工程固定资产投资的合理布局,以便更好发挥投资效果。 一、固定资产投资效果的回顾 铁坑铁矿自1960年建矿到1990年,共完成基建固定资产投资 61 87万元, 30年来该矿共采出原矿458.08万t,为钢铁厂提供合格块矿66.65万t,铁精矿粉181.27万t,促进了钢铁工业的发展。但24年出现亏损,利税总额为-2 632.68万元。
This paper intends to analyze the investment in fixed assets of Tiekeng Iron Mine, summarizes the experiences and lessons, and tries to explore the rational layout of the investment in fixed assets in the expansion project in order to give better play to the investment results. First, the review of the effect of investment in fixed assets Tiekeng iron mine construction in 1960 to 1990, completed a total investment of 61.87 million yuan in infrastructure investment in fixed assets, 30 mine mine a total of 4.5808 million tons of ore, steel mills to provide qualified block 666,500 tons of ore and 1,821,700 tons of iron ore concentrate, which promoted the development of the steel industry. However, a loss occurred in 24 years with a total profit and tax of -26,326,800 yuan.