沈阳市百货公司北市百货商店营业楼工程由沈阳市第三建筑工程公司施工。营业楼工程马赛克总量为980.26m~2,其中室内48根圆柱马赛克工程量为308m~2。一、工艺流程施工准备→测量放线→凿毛→基层处理→绑钢筋网→清扫、浇水浸润→刷107胶素水泥浆→贴竖向玻璃条→打→遍底灰→模具找平→打二遍底灰→模具找平→结合层水泥素灰→模具找平→弹线粘贴马赛克→润水→检查调整→拨缝→擦缝→养护。二、施工要点及要求 1.施工准备: (1)制定具体节点镶贴构造方案。
The Shenyang City Department Store’s North City Department Store’s business building project was constructed by Shenyang Third Construction Engineering Company. The total number of mosaics for business buildings is 980.26m~2, of which 48 cylindrical mosaics for indoor projects are 308m~2. First, the process of construction preparation → measuring line → cutting hair → grassroots processing → tied steel mesh → cleaning, water infiltration → brush 107 glue cement slurry → stick vertical glass bar → hit → over the bottom gray → mold leveling → hit Second time bottom ash → mold leveling → cement layer gray cement → mold leveling → paste line paste paste → water → inspection and adjustment → picks → wipes → curing. Second, the construction points and requirements 1. Construction preparation: (1) the development of a specific node mosaic layout program.